Surkhi is added to lime mortar to

  • a)
    prevent shrinkage

  • b)
    decrease setting time

  • c)
    impart hydraulicity

  • d)
    increase bulk

Correct answer is option 'C'. Can you explain this answer?
Verified Answer
Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting...
Correct Answer :- c
Explanation : Surkhi is an alternate form of sand with some additional properties of strength and hydraulicity.
View all questions of this test
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer?
Question Description
Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Surkhi is added to lime mortar toa)prevent shrinkageb)decrease setting timec)impart hydraulicityd)increase bulkCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev