Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  If P is the percentage of water required forn... Start Learning for Free
If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, is
  • a)
    0.70 P
  • b)
    0.75 P
  • c)
    0.80 P
  • d)
    0.85 P
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
If P is the percentage of water required fornormal consistency, water ...
To determine the initial setting time of cement, water is added to the cement paste until it reaches normal consistency. The normal consistency is defined as the percentage of water required to produce a paste that has a standard thickness and is able to retain its shape.

Let's assume that the percentage of water required for normal consistency is P.

To determine the initial setting time, additional water needs to be added to the cement paste. The amount of water added is usually expressed as a percentage of the water required for normal consistency.

Let's denote the percentage of additional water as x.

According to the given options, we need to find the value of x that represents the percentage of water to be added for the determination of initial setting time.

To find the value of x, we can use the formula:

Total percentage of water = Percentage of water for normal consistency + Percentage of additional water

In this case, the total percentage of water is 100% because it represents the total amount of water in the cement paste.

So, we can write the equation as:

100 = P + x

Now, let's solve for x:

x = 100 - P

This means that the percentage of additional water is equal to 100 minus the percentage of water required for normal consistency.

Comparing this equation with the given options, we can see that option D, 0.85P, matches the equation:

x = 100 - P = 0.85P

Therefore, the correct answer is option D, 0.85P.
Free Test
Community Answer
If P is the percentage of water required fornormal consistency, water ...
.85 - initial and final setting test
.78 - soundness test
....rat lo ...
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer?
Question Description
If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer?.
Solutions for If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If P is the percentage of water required fornormal consistency, water to be added fordetermination of initial setting time, isa)0.70 Pb)0.75 Pc)0.80 Pd)0.85 PCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.