Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  A 600 mm diameter RCC sewer is laid at a slop... Start Learning for Free
A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s?
Most Upvoted Answer
A 600 mm diameter RCC sewer is laid at a slope to developed a velocity...
Solution:

Given data,

Diameter of sewer (D) = 600 mm = 0.6 m

Velocity of flow at full capacity (V1) = 0.6 m/s

Manning's constant (n) = 0.013 (dimensionless)

Let's assume the depth of flow at half capacity (y) = 0.5D = 0.5 x 0.6 = 0.3 m

We know that the discharge (Q) in a sewer is given by the formula,

Q = (1/n) x A x R^2/3 x S^1/2

Where,

A = Cross-sectional area of flow

R = Hydraulic radius

S = Slope of sewer

At full capacity, the cross-sectional area can be calculated as follows,

A1 = π/4 x D^2 = π/4 x (0.6)^2 = 0.2827 m^2

The hydraulic radius can be calculated as follows,

R1 = A1/P

Where,

P = Wetted perimeter

P1 = π x D

R1 = 0.2827/1.88496 = 0.1499 m

Substituting the values in the formula of discharge, we get

0.6 = (1/0.013) x 0.2827 x (0.1499)^2/3 x S^1/2

S = 0.0012

Now, let's calculate the velocity of flow at half capacity,

At half capacity, the cross-sectional area can be calculated as follows,

A2 = π/4 x D^2 x y/ D = π/4 x (0.6)^2 x 0.5 = 0.1413 m^2

The hydraulic radius can be calculated as follows,

R2 = A2/P

Where,

P2 = π x D + 2 x (0.6/2) x cos^-1(1-2y/D)

P2 = π x 0.6 + 2 x (0.6/2) x cos^-1(1-2x0.3/0.6) = 1.88496 m

R2 = 0.1413/1.88496 = 0.0749 m

Substituting the values in the formula of discharge, we get

Q = (1/0.013) x 0.1413 x (0.0749)^2/3 x 0.0012^1/2

Q = 0.0568 m^3/s

The velocity of flow at half capacity can be calculated as follows,

V2 = Q/A2

V2 = 0.0568/0.1413 = 0.402 m/s

Therefore, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly 0.4 m/s.

Hence, the correct option is (a) 0.3 m/s.
Community Answer
A 600 mm diameter RCC sewer is laid at a slope to developed a velocity...
A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s?
Question Description
A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s?.
Solutions for A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s? defined & explained in the simplest way possible. Besides giving the explanation of A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s?, a detailed solution for A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s? has been provided alongside types of A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s? theory, EduRev gives you an ample number of questions to practice A 600 mm diameter RCC sewer is laid at a slope to developed a velocity of flow of 0.6 m/s while just running full.When the sewer is running exactly half-full, the velocity of flow taking Manning's constant to be equal to 0.013 is nearly (a) 0.3 m/s (b) 0.6 m/s (c) 0.9 m/s (d) 1.2 m/s? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev