A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5th of the work was done. How many more men must be employed so that the work may be finished in time?
  • a)
    35
  • b)
    60
  • c)
    48
  • d)
    30
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
A contractor undertook to do a work in 60 days and employed 30 men to ...
GIVEN:
A contractor undertook to do a work in 60 days and employed 30 men to do it.
After 45 days he found that only 3/5th of the work was done
FORMULA USED:
(M1D1)/(W1) = (M2D2)/(W2
CALCULATION:
(45 × 30)/(3/5) = (M2 ×15)/(2/5) 
M2 = (5 × 45 × 30 × 2)/(15 × 5 × 3)  = 60 men 
Required men = 60 – 30 = 30 men
View all questions of this test
Most Upvoted Answer
A contractor undertook to do a work in 60 days and employed 30 men to ...
GIVEN:
A contractor undertook to do a work in 60 days and employed 30 men to do it.
After 45 days he found that only 3/5th of the work was done
FORMULA USED:
(M1D1)/(W1) = (M2D2)/(W2
CALCULATION:
(45 × 30)/(3/5) = (M2 ×15)/(2/5) 
M2 = (5 × 45 × 30 × 2)/(15 × 5 × 3)  = 60 men 
Required men = 60 – 30 = 30 men
Explore Courses for Defence exam
A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer?
Question Description
A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer? for Defence 2024 is part of Defence preparation. The Question and answers have been prepared according to the Defence exam syllabus. Information about A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Defence 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer?.
Solutions for A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Defence. Download more important topics, notes, lectures and mock test series for Defence Exam by signing up for free.
Here you can find the meaning of A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer?, a detailed solution for A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A contractor undertook to do a work in 60 days and employed 30 men to do it. After 45 days he found that only 3/5thof the work was done. How many more men must be employed so that the work may be finished in time?a)35b)60c)48d)30Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Defence tests.
Explore Courses for Defence exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev