Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?
  • a)
    5 days
  • b)
    8 days
  • c)
    6 days
  • d)
    4 days
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
Ram can complete a job in 15 days. Shyam alone can complete the same j...
GIVEN:
Ram can complete a job in 15 days
Shyam can complete the same job in 10 days
Ram works for 9 days and then the remaining job is completed by Shyam
CALCULATION:
Ram’s 1 - day work = 1/15
∴ Ram’s 9 days’ work = 9/15 = 3/5
∴ Remaining work = 1 – 3/5 = 2/5 part of the work.
Shyam completes 1 work in 10 days.
∴ Shyam will complete 2/5th part of the work in 10 × 2/5 = 4 days.
View all questions of this test
Most Upvoted Answer
Ram can complete a job in 15 days. Shyam alone can complete the same j...
Given data:
Ram completes the job in 15 days
Shyam completes the job in 10 days
Ram works for 9 days

To find:
The number of days Shyam will take to complete the remaining job alone.

Solution:
Let the total work be 150 units (LCM of 15 and 10).
Ram's efficiency = 150/15 = 10 units/day
Shyam's efficiency = 150/10 = 15 units/day

Ram works for 9 days, so the work completed by him = 10 * 9 = 90 units
The remaining work = 150 - 90 = 60 units

Now, Shyam has to complete the remaining 60 units of work.
Shyam's efficiency = 15 units/day
Time taken by Shyam to complete the remaining work = 60/15 = 4 days

Therefore, the answer is option D, i.e., Shyam will take 4 days to complete the remaining job alone.
Explore Courses for Defence exam
Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer?
Question Description
Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer? for Defence 2024 is part of Defence preparation. The Question and answers have been prepared according to the Defence exam syllabus. Information about Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Defence 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer?.
Solutions for Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Defence. Download more important topics, notes, lectures and mock test series for Defence Exam by signing up for free.
Here you can find the meaning of Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Ram can complete a job in 15 days. Shyam alone can complete the same job in 10 days. Ram works for 9 days and then the remaining job is completed by Shyam. How many days will it take shyam to complete the remaining job alone?a)5 daysb)8 daysc)6 daysd)4 daysCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Defence tests.
Explore Courses for Defence exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev