Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  Free float is mainly used toa)Identify the ac... Start Learning for Free
Free float is mainly used to
  • a)
    Identify the activities which can be delayed without affecting the total float of preceding activity
  • b)
    Identify the activities, which can be delayed without affecting the total float of succeeding activity
  • c)
    Establish priorities
  • d)
    None of the above
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Free float is mainly used toa)Identify the activities which can be del...
The free float for activity i - j is the difference between its earliest finish time and the earliest finish time for its success or activity.
View all questions of this test
Most Upvoted Answer
Free float is mainly used toa)Identify the activities which can be del...
Introduction:
Free float is a term used in project management to identify the amount of time an activity can be delayed without affecting the total float of the succeeding activity. It helps in scheduling and decision-making during the project execution phase. Free float is an important concept in critical path analysis and is used to optimize project schedules.

Explanation:
The correct answer is option 'B' - Free float is mainly used to identify the activities which can be delayed without affecting the total float of the succeeding activity. Let's understand why this is the case:

1. Definition of Free Float:
Free float is the amount of time that an activity can be delayed without delaying the start of any dependent activities. It represents the flexibility in scheduling a particular activity without impacting the overall project timeline.

2. Identifying activities that can be delayed:
By calculating the free float for each activity in a project schedule, project managers can identify the activities that have flexibility in their start and finish dates. These activities can be delayed or rescheduled without causing a delay to the succeeding activities.

3. Focus on succeeding activities:
The main purpose of analyzing free float is to determine the activities that can be delayed without impacting the total float of the succeeding activities. Total float is the amount of time that an activity can be delayed without delaying the project completion date. By focusing on the free float of succeeding activities, project managers can make informed decisions about which activities can be delayed to optimize the project schedule.

4. Optimal scheduling:
By utilizing the information provided by free float, project managers can prioritize activities and allocate resources effectively. They can identify activities with high free float and prioritize them accordingly. This helps in optimizing the project schedule and ensures that critical activities are completed on time.

5. Impact on project timeline:
If an activity with zero free float is delayed, it will directly impact the start of the succeeding activities and may cause a delay in the project timeline. On the other hand, if an activity has a significant free float, it can be delayed without affecting the overall project schedule.

Conclusion:
Free float is a valuable tool in project management that helps in identifying activities that can be delayed without affecting the total float of the succeeding activities. By analyzing free float, project managers can make informed decisions about scheduling and resource allocation, ultimately optimizing the project schedule and ensuring timely completion.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer?
Question Description
Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Free float is mainly used toa)Identify the activities which can be delayed without affecting the total float of preceding activityb)Identify the activities, which can be delayed without affecting the total float of succeeding activityc)Establish prioritiesd)None of the aboveCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev