PERT stands for which of the following?
  • a)
    Period estimation and revision technique
  • b)
    Project estimation and revision technique 
  • c)
    Project evaluation and revision technique
  • d)
    Programme evaluation and review technique 
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
PERT stands for which of the following?a)Period estimation and revisio...
PERT (Program (Project) Management and Review Technique) and CPM (Critical Path Method) are the two network based project management techniques, which exhibit the flow and sequence of the activities and events.
View all questions of this test
Most Upvoted Answer
PERT stands for which of the following?a)Period estimation and revisio...
Pertaining to the given question:
The correct answer is option D: Programme evaluation and review technique (PERT). PERT is a project management technique that is used to analyze and represent the tasks involved in completing a project. It is commonly used in large-scale projects where there are numerous interdependent activities and uncertainties.

Explanation:
1. Programme evaluation and review technique (PERT):
PERT is a project management technique that was developed in the 1950s by the U.S. Navy to manage complex defense projects. It is a network-based scheduling technique that allows project managers to evaluate the time and resources required to complete a project.

2. Project estimation and revision technique:
This option is incorrect because it does not accurately describe the purpose of PERT. While PERT does involve estimating project timelines and making revisions, it is not solely focused on estimation and revision but also on evaluation and review.

3. Project evaluation and revision technique:
This option is incorrect because it does not accurately describe the purpose of PERT. PERT does involve project evaluation and revision, but it is not solely focused on these activities. PERT is a comprehensive project management technique that involves analyzing and representing project tasks, estimating timelines, and making revisions as necessary.

4. Period estimation and revision technique:
This option is incorrect because it does not accurately describe the purpose of PERT. While PERT does involve estimating project timelines and making revisions, it is not solely focused on period estimation and revision. PERT is a comprehensive project management technique that involves analyzing and representing project tasks, estimating timelines, and making revisions as necessary.

In conclusion, PERT stands for Programme Evaluation and Review Technique. It is a project management technique that is used to analyze and represent project tasks, estimate timelines, and make revisions as necessary. PERT is commonly used in large-scale projects where there are numerous interdependent activities and uncertainties.
Explore Courses for Defence exam
PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer?
Question Description
PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer? for Defence 2024 is part of Defence preparation. The Question and answers have been prepared according to the Defence exam syllabus. Information about PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Defence 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer?.
Solutions for PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Defence. Download more important topics, notes, lectures and mock test series for Defence Exam by signing up for free.
Here you can find the meaning of PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice PERT stands for which of the following?a)Period estimation and revision techniqueb)Project estimation and revision techniquec)Project evaluation and revision techniqued)Programme evaluation and review techniqueCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Defence tests.
Explore Courses for Defence exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev