Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   Consider the following 2 job and M-Machine p... Start Learning for Free
Consider the following 2 job and M-Machine problem
Job1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)
Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)
Find the make span.
  • a)
    10
  • b)
    10
Correct answer is between ' 10, 10'. Can you explain this answer?
Verified Answer
Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours...
Make span = 10 hours
View all questions of this test
Most Upvoted Answer
Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours...
Make span refers to the total time required to complete all the jobs in a given scheduling problem. In this case, we have two jobs and three machines. Let's analyze the given problem to find the make span.

Job 1:
The first job starts with the lathe machine, which takes 2 hours to complete. After that, it moves to the milling machine, which takes 1 hour. Finally, it goes to the drilling machine, which requires 4 hours to finish.

Job 2:
The second job begins with the milling machine, which takes 1 hour. Then it moves to the lathe machine, which requires 3 hours. Lastly, it goes to the drilling machine, which takes 3 hours to complete.

To find the make span, we need to consider the longest path or the maximum time required to complete all the jobs.

Lathe Machine:
Both jobs require the lathe machine, but the lathe machine in job 2 takes 3 hours, which is longer than the 2 hours required in job 1. So, we consider the 3 hours.

Milling Machine:
Job 1 requires 1 hour on the milling machine, while job 2 also requires 1 hour. Hence, we consider the maximum time, which is 1 hour.

Drilling Machine:
Job 1 requires 4 hours on the drilling machine, while job 2 requires 3 hours. Here, we consider the maximum time, which is 4 hours.

Now, we add up the maximum times for each machine to find the make span:

Make span = Lathe + Milling + Drilling
= 3 hours + 1 hour + 4 hours
= 8 hours

Therefore, the make span for the given problem is 8 hours.

The correct answer is not between 10 and 10 (as mentioned in the question), but rather the make span is 8 hours.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer?
Question Description
Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer?.
Solutions for Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer?, a detailed solution for Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer? has been provided alongside types of Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following 2 job and M-Machine problemJob1 Lathe (2 hours) → Milling (1 hour)→→Drilling (4hours)Job 2 Milling (1 hour)→ Lathe (3 hours) → Drilling (3 hours)Find the make span.a) 10b) 10Correct answer is between ' 10, 10'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev