In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________
  • a)
    4065
  • b)
    4068
Correct answer is between ' 4065, 4068'. Can you explain this answer?
Verified Answer
In an industry, two bin system is used to control inventory for a par...
In two bin system order is placed after consuming 1st bin So, ordering quantity will be 1200 units
= Rs. 4066.67
View all questions of this test
Most Upvoted Answer
In an industry, two bin system is used to control inventory for a par...
In two bin system order is placed after consuming 1st bin So, ordering quantity will be 1200 units
= Rs. 4066.67
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer?
Question Description
In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer?.
Solutions for In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer?, a detailed solution for In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer? has been provided alongside types of In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In an industry, two bin system is used to control inventory for a particular component. The first bin hold 1200 units and the second bin holds 800 units. When first bin gets empty second bin is consumed during the lead time. The annual usage of the component is 40,000 units. The cost to place an order is around Rs. 50, the annual holding cost per unit is Rs. 4. The total variable cost for the two-bin approach is __________a) 4065b) 4068Correct answer is between ' 4065, 4068'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev