A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given as
What is the probability of completing the project in 29 days?
  • a)
    0.14
  • b)
    0.16
Correct answer is between ' 0.14, 0.16'. Can you explain this answer?
Verified Answer
A project consists of activities for which exact completion times are...
Longer path is the path which is having maximum value of mean. It is the critical path.
Critical path duration = 32 days = μ variance = 9 = σ2
Standard deviation = σ = 3
z = −1
At z = −1; P = 16%
= 0.16
View all questions of this test
Most Upvoted Answer
A project consists of activities for which exact completion times are...
Longer path is the path which is having maximum value of mean. It is the critical path.
Critical path duration = 32 days = μ variance = 9 = σ2
Standard deviation = σ = 3
z = −1
At z = −1; P = 16%
= 0.16
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer?
Question Description
A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer?.
Solutions for A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer?, a detailed solution for A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer? has been provided alongside types of A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given asWhat is the probability of completing the project in 29 days?a) 0.14b) 0.16Correct answer is between ' 0.14, 0.16'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev