Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  Consider the following statements:The critica... Start Learning for Free
Consider the following statements:

The critical path in a network plan of a project

1. helps in planning efficient time schedule

2. indicates the shortest path in time 

3. helps in crashing the project judiciously

4. helps in encouraging-discipline in execution

Which of these statements are correct?

  • a)
    1, 3 and 4

  • b)
    1, 2, 3 and 4

  • c)
    1 and 4

  • d)
    2 and 3 

Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Consider the following statements:The critical path in a network plan ...


  1. Helps in planning efficient time schedule:



    • The critical path method (CPM) is used to identify the longest sequence of tasks in a project that must be completed on time for the project to be finished by its deadline. Knowing the critical path helps in planning an efficient time schedule by focusing on these critical tasks.




  2. Indicates the shortest path in time:



    • This statement is incorrect. The critical path actually represents the longest path through the project, not the shortest. It determines the minimum project duration by identifying the sequence of dependent tasks that have the longest total duration.




  3. Helps in crashing the project judiciously:



    • Crashing a project involves adding resources to critical path tasks to complete them more quickly, thus reducing the project duration. Identifying the critical path is crucial for effective crashing, as only tasks on the critical path will affect the overall project completion time.




  4. Helps in encouraging discipline in execution:



    • By highlighting the tasks that cannot be delayed without affecting the project completion date, the critical path helps enforce discipline in execution. Project managers and team members can focus their attention on critical tasks to ensure they stay on track.





Therefore, the correct answer is: 1, 3 and 4
View all questions of this test
Most Upvoted Answer
Consider the following statements:The critical path in a network plan ...
Explanation:

Critical path is an important concept in project management that helps in planning and scheduling of a project. The critical path is the longest path in a network diagram, which determines the minimum time required to complete the project. It is important to identify the critical path in a project as it helps in optimizing the project schedule and managing resources efficiently.

Let's discuss the given statements one by one:

1. Helps in planning efficient time schedule:
The critical path helps in identifying the sequence of activities that need to be completed in the shortest possible time. This helps in planning an efficient time schedule for the project. The project manager can allocate resources and plan the activities more effectively, resulting in timely completion of the project.

2. Indicates the shortest path in time:
This statement is incorrect. The critical path is not the shortest path in time, but the longest path in a network diagram. It is the path that determines the minimum time required to complete the project.

3. Helps in crashing the project judiciously:
Crashing the project means reducing the project duration by increasing the resources or activities. The critical path helps in identifying the activities that have the least amount of slack or float, which means they cannot be delayed without delaying the project. By focusing on these activities, the project manager can determine which activities can be crashed to reduce the project duration without affecting the critical path. Thus, it helps in crashing the project judiciously.

4. Helps in encouraging-discipline in execution:
The critical path helps in encouraging discipline in execution as it provides a clear roadmap of activities that need to be completed for timely completion of the project. The project manager can monitor the progress of activities and take corrective actions if required to ensure that the project is completed on time.

Therefore, the correct statements are 1, 3, and 4.
Free Test
Community Answer
Consider the following statements:The critical path in a network plan ...
Critical Path in Network Plan

The critical path in a network plan of a project refers to the sequence of activities that must be completed within the given timeframe for the project to be completed on time. It is an important tool in project management and has several benefits. The correct statements regarding the critical path are:

1. Helps in planning efficient time schedule: The critical path helps in identifying the activities that are critical to the project's success and those that can be delayed without affecting the project's timeline. By focusing on the critical path activities, project managers can plan an efficient time schedule that ensures the project is completed on time.

2. Indicates the shortest path in time: The critical path is the longest sequence of activities that must be completed to finish the project on time. While it is not necessarily the shortest path in time, it is the path that cannot be delayed without delaying the project.

3. Helps in crashing the project judiciously: Crashing refers to shortening the project's duration by adding resources to critical path activities. The critical path helps in identifying the activities that can be crashed to reduce the project's duration without affecting its quality.

4. Helps in encouraging discipline in execution: Since the critical path represents the activities that must be completed on time, it helps in encouraging discipline in execution by ensuring that these activities are given priority and completed on time.

Therefore, the correct statements are 1, 3, and 4, making option A the correct answer.
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer?
Question Description
Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer?.
Solutions for Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer?, a detailed solution for Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following statements:The critical path in a network plan of a project1. helps in planning efficient time schedule2. indicates the shortest path in time3. helps in crashing the project judiciously4. helps in encouraging-discipline in executionWhich of these statements are correct?a)1, 3 and 4b)1, 2, 3 and 4c)1 and 4d)2 and 3Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev