A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is
[2005]
  • a)
    45
  • b)
    50
  • c)
    55
  • d)
    60
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
A welding operation is time-studied during which an operator was pace-...
Normal time = Actual Time × Rating factor.
Standard Production rate = 
View all questions of this test
Most Upvoted Answer
A welding operation is time-studied during which an operator was pace-...
Normal time = Actual Time × Rating factor.
Standard Production rate = 
Free Test
Community Answer
A welding operation is time-studied during which an operator was pace-...
Given data:
- Operator's pace rating = 120%
- Average time taken by operator for producing weld-joint = 8 minutes
- Total allowances allowed = 10%

To find:
Expected standard production rate of the weld-joint (in units per 8-hour day)

Approach:
1. Calculate the standard time for producing one weld-joint.
2. Calculate the total working time available in an 8-hour day.
3. Calculate the expected production rate by dividing the total working time by the standard time for one weld-joint.
4. Apply the allowances to obtain the final expected standard production rate.

Solution:

Step 1: Calculation of Standard Time
The standard time is the time required to produce one weld-joint at 100% efficiency. It is calculated by dividing the actual time taken by the operator by the operator's pace rating.

Standard Time = (Actual Time / Pace Rating) = (8 minutes / 120%) = (8 minutes / 1.2) = 6.67 minutes

Step 2: Calculation of Total Working Time
In an 8-hour day, there are 480 minutes available for work.

Total Working Time = 8 hours × 60 minutes/hour = 480 minutes

Step 3: Calculation of Expected Production Rate
The expected production rate is calculated by dividing the total working time by the standard time.

Expected Production Rate = Total Working Time / Standard Time = 480 minutes / 6.67 minutes = 71.97 weld-joints

Step 4: Application of Allowances
10% allowances are allowed for this operation. To calculate the final expected standard production rate, we deduct the allowances from the expected production rate.

Final Expected Standard Production Rate = Expected Production Rate - (Expected Production Rate × Allowances / 100)
= 71.97 - (71.97 × 10 / 100)
= 71.97 - 7.20
= 64.77 weld-joints

Conclusion:
The expected standard production rate of the weld-joint, after applying 10% allowances, is approximately 64.77 weld-joints. Since this is not one of the given answer options, we round it to the nearest whole number, which is 65. Therefore, the correct answer is option 'A' (45).
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer?
Question Description
A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer?.
Solutions for A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer?, a detailed solution for A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is[2005]a)45b)50c)55d)60Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev