Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.

Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.) 
  • a)
    150% 
  • b)
    225% 
  • c)
    270% 
  • d)
    240%
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Sarp Infotech Solutions Software Company before selling a package to i...
% change in the cost incurred in the fifth month,

= 150%
This question is part of UPSC exam. View all CAT courses
Most Upvoted Answer
Sarp Infotech Solutions Software Company before selling a package to i...
% change in the cost incurred in the fifth month,

= 150%
Community Answer
Sarp Infotech Solutions Software Company before selling a package to i...
% change in the cost incurred in the fifth month,

= 150%
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Similar CAT Doubts

Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer?
Question Description
Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer?.
Solutions for Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer?, a detailed solution for Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.Q. Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)a)150%b)225%c)270%d)240%Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev