Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800?
Most Upvoted Answer
Determine the fixed component is the semi varible cost of m/s model ho...
Fixed and Semi-Variable Costs for M/S Model House LTD

Fixed Costs

Fixed costs are expenses that do not vary with the level of production or sales. They are the costs that a business incurs regardless of how much it produces or sells. In the case of M/S Model House LTD, the fixed cost component is not given explicitly in the question. Therefore, we can assume that fixed costs are not provided or negligible in this scenario.

Semi-Variable Costs

Semi-variable costs, also known as mixed costs, are expenses that have both fixed and variable components. These costs are partly fixed and partly variable, which means they change with the level of production or sales, but not in direct proportion. The semi-variable cost of producing 5000 units for M/S Model House LTD is given as RS 24000, and the semi-variable cost for producing an additional 1000 units is RS 1800.

Calculation of Fixed and Variable Components

To calculate the fixed and variable components of the semi-variable costs, we can use the high-low method. This method uses the highest and lowest levels of production to determine the variable cost per unit and the fixed cost component.

Using the data given in the question, we can calculate the variable cost per unit as follows:

Variable cost per unit = (Semi-variable cost at high level - Semi-variable cost at low level) / (High level - Low level)
= (RS 25800 - RS 24000) / (6000 - 5000)
= RS 1800 / 1000
= RS 1.8

Now that we know the variable cost per unit, we can calculate the fixed cost component as follows:

Fixed cost component = Total semi-variable cost - (Variable cost per unit x Total units produced)
= RS 24000 - (RS 1.8 x 5000)
= RS 24000 - RS 9000
= RS 15000

Therefore, the fixed cost component for M/S Model House LTD is RS 15000, and the variable cost per unit is RS 1.8.
Community Answer
Determine the fixed component is the semi varible cost of m/s model ho...
15000
Explore Courses for Defence exam

Similar Defence Doubts

Read the passage and answer the following questions.Unprecedented rainfall in Himalayan foothills during last couple of days and wide spread inundation have once again brought the old Indo-Bhutan trans boundary issue of dolomite contamination of land and its bite on tea economy of Dooars region in northern West Bengal into surface. Flow of water, highly contaminated with dolomite from illegal mines in Bhutan, through rivers in Dooars region in Alipurduar district had always remained a concern for the local tea dependent economy. “The ground water contamination keeps on damaging soil hampering production. But this time, large scale inundation of garden has caused heavy damage of bushes too,” said planters there. Large section of near 150-tea gardens in the region, producing around 20% of the countrys total yield, are now inundated under water of around 70 streams and rivers coming down from Bhutan. Industry experts have estimated the immediate loss as of around Rs 200 Crore. In addition to that, “Rejuvenation cost of dolomite affected bushes will significantly increase the loss,” said S. Guhathakurata, Secretary of Dooars Branch of Indian Tea Association. In the sixties, dolomite was an important export item of Bhutan to India. Although the official trade took a downturn in 80’s, complains are still there about continuation of open-pit, illegal mines. Bhutan holds a reserve of 13.5 billion ton, one of the highest in the world. This builds up dolomite rich debris on river bed reducing their water retaining capacity and contaminating ground water.Q.Which of the following has a meaning similar to the word inundation?

Read the passage and answer the following questions.Unprecedented rainfall in Himalayan foothills during last couple of days and wide spreadinundationhave once again brought the old Indo-Bhutan trans boundary issue of dolomite contamination of land and its bite on tea economy of Dooars region in northern West Bengal into surface.Flow of water, highly contaminated with dolomite from illegal mines in Bhutan, through rivers in Dooars region in Alipurduar district had always remained a concern for the local tea dependent economy. “The ground water contamination keeps on damaging soil hampering production. But this time, large scale inundation of garden has caused heavy damage of bushes too,” said planters there. Large section of near 150-tea gardens in the region, producing around 20% of the countrys total yield, are now inundated under water of around 70 streams and rivers coming down from Bhutan.Industry experts have estimated the immediate loss as of around Rs 200 Crore. In addition to that, “Rejuvenation cost of dolomite affected bushes will significantly increase the loss,” said S. Guhathakurata, Secretary of Dooars Branch of Indian Tea Association.In the sixties, dolomite was an important export item of Bhutan to India. Although the official trade took a downturn in 80’s, complains are still there about continuation of open-pit, illegal mines. Bhutan holds a reserve of 13.5 billion ton, one of the highest in the world. This builds up dolomite rich debris on river bed reducing their water retaining capacity and contaminating ground water.Q.Why is the situation worse than before?

Read the passage and answer the following questions.Unprecedented rainfall in Himalayan foothills during last couple of days and wide spreadinundationhave once again brought the old Indo-Bhutan trans boundary issue of dolomite contamination of land and its bite on tea economy of Dooars region in northern West Bengal into surface.Flow of water, highly contaminated with dolomite from illegal mines in Bhutan, through rivers in Dooars region in Alipurduar district had always remained a concern for the local tea dependent economy. “The ground water contamination keeps on damaging soil hampering production. But this time, large scale inundation of garden has caused heavy damage of bushes too,” said planters there. Large section of near 150-tea gardens in the region, producing around 20% of the countrys total yield, are now inundated under water of around 70 streams and rivers coming down from Bhutan.Industry experts have estimated the immediate loss as of around Rs 200 Crore. In addition to that, “Rejuvenation cost of dolomite affected bushes will significantly increase the loss,” said S. Guhathakurata, Secretary of Dooars Branch of Indian Tea Association.In the sixties, dolomite was an important export item of Bhutan to India. Although the official trade took a downturn in 80’s, complains are still there about continuation of open-pit, illegal mines. Bhutan holds a reserve of 13.5 billion ton, one of the highest in the world. This builds up dolomite rich debris on river bed reducing their water retaining capacity and contaminating ground water.Q.Which of the following would aggravate the loss?

Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800?
Question Description
Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800? for Defence 2024 is part of Defence preparation. The Question and answers have been prepared according to the Defence exam syllabus. Information about Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800? covers all topics & solutions for Defence 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800?.
Solutions for Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800? in English & in Hindi are available as part of our courses for Defence. Download more important topics, notes, lectures and mock test series for Defence Exam by signing up for free.
Here you can find the meaning of Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800? defined & explained in the simplest way possible. Besides giving the explanation of Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800?, a detailed solution for Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800? has been provided alongside types of Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800? theory, EduRev gives you an ample number of questions to practice Determine the fixed component is the semi varible cost of m/s model house LTD. semi fixed cost on producing 5000 units RS 24000 semi variable expenses and producing on additional 1000 units RS 1800? tests, examples and also practice Defence tests.
Explore Courses for Defence exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev