In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively are
  • a)
    SPT, EDD
  • b)
    EDD, SPT
  • c)
    EDD, LPT
  • d)
    SPT, FCFS
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
In sequencing for minimizing mean tardiness and average in process in...
**Explanation:**

The sequencing rules used in minimizing mean tardiness and average in-process inventory are **EDD** (Earliest Due Date) and **SPT** (Shortest Processing Time).

**1. EDD (Earliest Due Date):**
- EDD is a scheduling rule that prioritizes jobs based on their due dates.
- Jobs with earlier due dates are given higher priority and are scheduled first.
- This rule aims to minimize the mean tardiness, which is the difference between the job completion time and its due date.
- By scheduling jobs with earlier due dates first, the overall tardiness is reduced, leading to a lower mean tardiness.

**2. SPT (Shortest Processing Time):**
- SPT is a scheduling rule that prioritizes jobs based on their processing times.
- Jobs with shorter processing times are given higher priority and are scheduled first.
- This rule aims to minimize the average in-process inventory, which is the average amount of work in progress at any given time.
- By scheduling jobs with shorter processing times first, the overall processing time is reduced, leading to a lower average in-process inventory.

**Why EDD and SPT are the correct choices:**
- Minimizing mean tardiness and average in-process inventory are two different objectives in sequencing.
- EDD is effective in minimizing mean tardiness because it prioritizes jobs based on their due dates, ensuring that jobs with earlier due dates are completed first.
- SPT is effective in minimizing average in-process inventory because it prioritizes jobs based on their processing times, ensuring that shorter jobs are completed first and the overall processing time is reduced.
- Combining EDD and SPT as sequencing rules allows for a balanced approach, addressing both objectives simultaneously.
- EDD ensures that jobs are completed on time, reducing tardiness, while SPT ensures that jobs are processed quickly, reducing in-process inventory.

Hence, the correct sequencing rules for minimizing mean tardiness and average in-process inventory are **EDD** (Earliest Due Date) and **SPT** (Shortest Processing Time), which corresponds to option **B**.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer?
Question Description
In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer?.
Solutions for In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In sequencing for minimizing mean tardiness and average in process inventory, the rules to be used respectively area) SPT, EDDb) EDD, SPTc) EDD, LPTd) SPT, FCFSCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev