Mechanical Engineering Exam  >  Mechanical Engineering Questions  >  The slack on various events at critical path ... Start Learning for Free
The slack on various events at critical path on a PERT/ CPM chart
  • a)
    remains constant
  • b)
    increases continuously
  • c)
    decreases continuously
  • d)
    may increase or decrease linearly
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
The slack on various events at critical path on a PERT/ CPM charta)rem...
Slack on various events at critical path on a PERT/CPM chart remains constant because:

Explanation:
PERT/CPM charts are used to manage and schedule complex projects. The critical path is the longest path in the network diagram, which determines the minimum time required to complete the project. Slack is the amount of time an activity can be delayed without delaying the project completion time. The events on the critical path have zero slack, which means any delay in these events will delay the project completion time.

The slack on various events at critical path remains constant because of the following reasons:

1. Critical Path:
The events on the critical path have zero slack, which means any delay in these events will delay the project completion time. As the slack is zero, it remains constant throughout the project.

2. Fixed duration:
The duration of the events on the critical path is fixed and cannot be changed without delaying the project completion time. Hence, the slack on these events remains constant.

3. Resource allocation:
The resources required for the events on the critical path are allocated in such a way that the duration of the events is minimized. This results in zero slack on these events, which remains constant.

4. Time management:
The project manager closely monitors the events on the critical path to ensure that they are completed on time. Any delay in these events will delay the project completion time, which is undesirable. Hence, the slack on these events remains constant.

Conclusion:
Hence, it can be concluded that the slack on various events at critical path on a PERT/CPM chart remains constant because the events on the critical path have zero slack, the duration of the events is fixed, the resources are allocated efficiently, and the project manager closely monitors the events to ensure on-time completion.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer?
Question Description
The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer?.
Solutions for The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The slack on various events at critical path on a PERT/ CPM charta)remains constantb)increases continuouslyc)decreases continuouslyd)may increase or decrease linearlyCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev