Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   Which one of the following is not a necessar... Start Learning for Free
Which one of the following is not a necessary information input to Material Requirements Planning?
  • a)
    Inventory on hand
  • b)
    Bill of materials
  • c)
    Sequence of operations on a job
  • d)
    Master production schedule (MPS)
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
Which one of the following is not a necessary information input to Ma...
Inventory on hand:
Inventory on hand refers to the quantity of materials or products that a company currently has in its possession. This information is necessary for material requirements planning (MRP) because it helps determine if there is enough inventory available to meet production demands. If the inventory on hand is insufficient, the MRP system can generate purchase orders or production orders to ensure that enough materials are available.

Bill of materials:
The bill of materials (BOM) is a detailed list of all the components and raw materials required to produce a finished product. It includes information such as part numbers, quantities, and descriptions. The BOM is a critical input to MRP because it provides the necessary information to calculate the requirements for each component based on the production schedule. Without a BOM, the MRP system would not be able to accurately determine the quantity of each component needed for production.

Master production schedule (MPS):
The master production schedule (MPS) is a plan that specifies the quantity and timing of finished products to be produced. It takes into account factors such as customer demand, production capacity, and inventory levels. The MPS is an essential input to MRP because it provides the information needed to determine the quantity and timing of component requirements. Without an MPS, the MRP system would not be able to generate accurate production orders or purchase orders.

Sequence of operations on a job:
The sequence of operations on a job refers to the specific order in which the manufacturing processes need to be performed to produce a finished product. This information is typically included in the routing or process sheet for each job. While the sequence of operations is important for production planning and scheduling, it is not a necessary input to MRP. MRP focuses on determining the material requirements based on the production schedule, inventory levels, and BOM. The sequence of operations is more relevant to shop floor control and scheduling activities.

Therefore, the correct answer is option C - Sequence of operations on a job. This information is not a necessary input to MRP.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer?
Question Description
Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer?.
Solutions for Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer?, a detailed solution for Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which one of the following is not a necessary information input to Material Requirements Planning?a) Inventory on handb) Bill of materialsc) Sequence of operations on a jobd) Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev