Mechanical Engineering Exam  >  Mechanical Engineering Questions  >  Which one of the following forecasting techni... Start Learning for Free
Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range? 
[1988]                                                            
  • a)
    Moving average
  • b)
    Exponential moving average
  • c)
    Regression analysis
  • d)
    Delphi                         
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
Which one of the following forecasting techniques is not suited for ma...
Short Range Production Planning and Forecasting Techniques

Short range production planning refers to the process of creating a detailed production schedule for the immediate future, typically for a period of a few weeks up to a few months. Effective short range planning and forecasting is critical for ensuring that production schedules are optimized for efficiency and that resources are used effectively.

There are several forecasting techniques that can be used for short range production planning, including moving averages, exponential moving averages, and regression analysis. However, there is one forecasting technique that is not well-suited for this purpose, and that is the Delphi method.

The Delphi Method

The Delphi method is a forecasting technique that is based on the input of a panel of experts. The experts are typically asked to provide their opinions on a particular topic or question, and these opinions are then aggregated and analyzed to generate a forecast.

While the Delphi method can be useful in certain contexts, it is not well-suited for short range production planning. This is because the Delphi method relies on the input of experts, and it can be difficult to gather and coordinate this input in a timely manner. Additionally, the Delphi method is often used for forecasting long-term trends and developments, rather than short-term production schedules.

Moving Averages

Moving averages are a common forecasting technique that is well-suited for short range production planning. This technique involves calculating the average of a set of data points over a specified period of time, and then using this average to make a forecast for the future.

Exponential Moving Averages

Exponential moving averages are similar to moving averages, but they give greater weight to more recent data points. This makes them particularly useful for short range forecasting, as they can capture changes in demand or production patterns more quickly than other techniques.

Regression Analysis

Regression analysis is another useful forecasting technique for short range production planning. This technique involves analyzing historical data to identify trends and patterns, and then using this information to generate a forecast for the future. Regression analysis can be particularly useful when there are multiple variables that affect production, such as changes in demand or fluctuations in resource availability.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer?
Question Description
Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer?.
Solutions for Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which one of the following forecasting techniques is not suited for making forecasts for planning Production schedules in the short range?[1988] a)Moving averageb)Exponential moving averagec)Regression analysisd)Delphi Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev