Class 12 Exam  >  Class 12 Questions  >  4 men and 6 women complete a piece of work in... Start Learning for Free
4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?
  • a)
    24 days
  • b)
    32 days
  • c)
    36 days
  • d)
    40 days
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
4 men and 6 women complete a piece of work in 8 days while 3 men and 7...
Given:
- 4 men and 6 women complete a piece of work in 8 days
- 3 men and 7 women complete the same work in 10 days

Let's assume that the amount of work done by each person in one day is the same.

Let's first find the amount of work done by each man and each woman in one day.

Let the work done by each man in one day be M, and the work done by each woman in one day be W.

From the given information, we can write the following equations:
4M + 6W = 1 (Equation 1) - Since 4 men and 6 women complete the work in 8 days
3M + 7W = 1 (Equation 2) - Since 3 men and 7 women complete the work in 10 days

Solving these equations will give us the values of M and W.

Multiplying Equation 1 by 3 and Equation 2 by 4, we get:
12M + 18W = 3 (Equation 3)
12M + 28W = 4 (Equation 4)

Subtracting Equation 3 from Equation 4, we get:
10W = 1

Therefore, W = 1/10

Substituting the value of W in Equation 1, we get:
4M + 6(1/10) = 1
4M + 3/5 = 1
4M = 1 - 3/5
4M = 2/5
M = 1/10

So, the work done by each man in one day is 1/10 and the work done by each woman in one day is 1/10.

Now, let's find how many days it will take for 10 women to complete the work.

Let the number of days required be D.

From the given information, we can write the equation:
10(1/10)D = 1

Simplifying, we get:
D = 1

Therefore, it will take 10 women 1 day to complete the work.

Since the options provided are in terms of days, the closest answer is 40 days (option D).

Hence, the correct answer is D) 40 days.
Free Test
Community Answer
4 men and 6 women complete a piece of work in 8 days while 3 men and 7...
Let 1 man's 1 day work be x and 1 woman's 1 day work be y. then
4x+6 y= 1/8 ...(1)
3x+7y = 1/10 ...(2)
Multiplying (1) by 3, (2) by 4 and subtracting, we get
10 y = (4/10- 3/8)
= (16-15)/40 = 1/40
⇒ y = 1/400
1 woman's 1 day work = 1/400
10 women's 1 day work = (1/400*10) = 1/40
Hence 10 women can finish the work in 40 days
Explore Courses for Class 12 exam
4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer?
Question Description
4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer? for Class 12 2024 is part of Class 12 preparation. The Question and answers have been prepared according to the Class 12 exam syllabus. Information about 4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Class 12 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer?.
Solutions for 4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Class 12. Download more important topics, notes, lectures and mock test series for Class 12 Exam by signing up for free.
Here you can find the meaning of 4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for 4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of 4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 4 men and 6 women complete a piece of work in 8 days while 3 men and 7 women complete it in 10 days. In how many days 10 women can finish the work?a)24 daysb)32 daysc)36 daysd)40 daysCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Class 12 tests.
Explore Courses for Class 12 exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev