In material requirements planning, which one of the following is not used as necessary information input?
  • a)
    Inventory status file
  • b)
    Bill of materials (BOM)
  • c)
    Scheduled receipts
  • d)
    Master production schedule (MPS)
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
In material requirements planning, which one of the following is not ...
The figure shows a 'Material Requirements Planning system'.
Free Test
Community Answer
In material requirements planning, which one of the following is not ...
Explanation:
Material requirements planning (MRP) is a production planning and inventory control system that helps manufacturers manage the production process. It involves determining the quantities and timing of raw materials, components, and subassemblies needed to produce finished goods.

Inventory status file:
The inventory status file is an important input in MRP. It contains information about the current inventory levels of raw materials, components, and finished goods. This information is necessary to determine the availability of materials for production and to calculate the reorder quantities.

Bill of materials (BOM):
The bill of materials (BOM) is another important input in MRP. It is a list of all the components, subassemblies, and raw materials required to produce a finished product. The BOM provides information on the quantities and relationships between the different parts, allowing MRP to calculate the material requirements based on the production schedule.

Scheduled receipts:
Scheduled receipts are also an important input in MRP. They refer to the planned delivery dates and quantities of incoming materials or components. This information helps MRP determine when and how much material will be available for production.

Master production schedule (MPS):
The master production schedule (MPS) is a key input in MRP. It is a plan that specifies the quantity and timing of finished goods production. The MPS provides information on the production requirements, allowing MRP to calculate the material requirements and schedule the production accordingly.

Correct answer:
The correct answer is option 'C' - Scheduled receipts. Scheduled receipts are not used as necessary information input in MRP. While they are important for determining the availability of materials, they are not directly used in the MRP calculations. Instead, MRP uses the inventory status file, BOM, and MPS to calculate the material requirements and schedule the production. Scheduled receipts are more relevant to materials planning and procurement processes.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer?
Question Description
In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer?.
Solutions for In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer?, a detailed solution for In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In material requirements planning, which one of the following is not used as necessary information input?a)Inventory status fileb)Bill of materials (BOM)c)Scheduled receiptsd)Master production schedule (MPS)Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev