Banking Exams Exam  >  Banking Exams Questions  >   Direction: Given below are quantities named ... Start Learning for Free
Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.
James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.
Quantity A: If James starts the work, then find the number of days required to complete the work.
Quantity B: If Jason starts the work, then find the number of days required to complete the work.
  • a)
    Quantity A ≥ Quantity B
  • b)
    Quantity A ≤ Quantity B
  • c)
    Quantity A > Quantity B
  • d)
    Quantity A < quantity="" />
  • e)
    Quantity A = Quantity B or No relation
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
Direction: Given below are quantities named A and B. Based on the giv...
Let, total units of work be 32 units then James does 2 units per day and Jason does 1 unit per day.
Quantity A:
⇒ 3 units are done in 2 days.
⇒ 30 units are done in 20 days.
On 21st day James does 2 units and work gets completed.
Quantity B:
⇒ 3 units are done in 2 days
⇒ 30 units are done in 20 days.
On 21st day Jason does 1 - unit work.
James completes the remaining one unit in another = 1/2 day
Total days = 21.5
∴ Quantity B > Quantity A
Explore Courses for Banking Exams exam

Similar Banking Exams Doubts

Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer?
Question Description
Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer? for Banking Exams 2024 is part of Banking Exams preparation. The Question and answers have been prepared according to the Banking Exams exam syllabus. Information about Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Banking Exams 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer?.
Solutions for Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams. Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Direction: Given below are quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of mathematics to choose among the possible answer.James and Jason work on alternate days and James can do a piece of work in 16 days while Jason can do the same work in 32 days.Quantity A: If James starts the work, then find the number of days required to complete the work.Quantity B: If Jason starts the work, then find the number of days required to complete the work.a)Quantity A ≥ Quantity Bb)Quantity A ≤ Quantity Bc)Quantity A > Quantity Bd)Quantity A e)Quantity A = Quantity B or No relationCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Banking Exams tests.
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev