Which of the following data is not required to prepare an estimate?
  • a)
    Amplitude
  • b)
    Drawings
  • c)
    Specifications
  • d)
    Rates
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
Which of the following data is not required to prepare an estimate?a)A...
Answer:

To prepare an estimate, various data and information are required. However, not all data are necessary for estimating the cost of a project. Among the options given, the data that is not required to prepare an estimate is the amplitude (option A).

Explanation:

To understand why amplitude is not required for estimating, let's briefly discuss the other options:

Drawings:
Drawings are an essential part of estimating because they provide a visual representation of the project. They include floor plans, elevations, sections, and other detailed drawings that help in understanding the scope of work and calculating the quantities of materials required.

Specifications:
Specifications outline the specific requirements and quality standards for the project. They provide detailed information about the materials to be used, construction methods, and other technical aspects. Estimators need specifications to accurately determine the cost of materials, labor, and equipment.

Rates:
Rates refer to the unit prices of various items and activities involved in the project. Estimators use rates to calculate the cost of materials, labor, and equipment based on the quantities obtained from the drawings and specifications. Rates are crucial for accurately estimating the total cost of a project.

Amplitude:
Amplitude, in the context of estimating, is not a relevant term or data. It typically refers to the maximum extent or measurement of a vibration or oscillation. In the construction estimation process, amplitude does not have any direct application or relevance. It is not a factor that affects the cost estimation or any other aspect of the project.

Therefore, among the given options, amplitude is the data that is not required to prepare an estimate. The other options, such as drawings, specifications, and rates, are essential components of the estimating process as they provide the necessary information for accurately calculating the cost of a construction project.
Free Test
Community Answer
Which of the following data is not required to prepare an estimate?a)A...
For preparing an estimate, data such as drawings, detailed specifications, rates, etc. is required. The drawings needed to prepare the estimate include plans, sections, elevations, etc.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer?
Question Description
Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer?.
Solutions for Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which of the following data is not required to prepare an estimate?a)Amplitudeb)Drawingsc)Specificationsd)RatesCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev