A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?
  • a)
    110
  • b)
    75
  • c)
    50
  • d)
    100
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
A certain number of men can finish a piece of work in 100 days. Howeve...
Given:
- Number of men required to finish the work in 100 days = x
- If there were 10 men less, then it would take 10 days more to finish the work

To Find:
- Number of men originally

Assumption:
- The amount of work is the same throughout the process

Explanation:

Let's assume that the total work is represented by W.

1. Work completed per day by x men = W/100
2. Work completed per day by (x-10) men = W/(100+10) = W/110

Since the amount of work is the same, we can equate these two expressions:

W/100 = W/110

Solving the equation:

Cross-multiplying the equation, we get:

110W = 100W

Simplifying the equation, we get:

10W = 0

Since the equation is not possible, it means that our assumption was wrong.

Conclusion:

We cannot determine the number of men originally based on the given information. The information provided is contradictory and does not lead to a valid solution.

Therefore, the correct answer is none of the given options.
Explore Courses for SSC CGL exam

Top Courses for SSC CGL

A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer?
Question Description
A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer? for SSC CGL 2024 is part of SSC CGL preparation. The Question and answers have been prepared according to the SSC CGL exam syllabus. Information about A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for SSC CGL 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer?.
Solutions for A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC CGL. Download more important topics, notes, lectures and mock test series for SSC CGL Exam by signing up for free.
Here you can find the meaning of A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer?, a detailed solution for A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A certain number of men can finish a piece of work in 100 days. However, if there were 10 men less, then it would take 10 days more for the work to be finished How many men were there originally?a)110b)75c)50d)100Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice SSC CGL tests.
Explore Courses for SSC CGL exam

Top Courses for SSC CGL

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev