Electrical Engineering (EE) Exam  >  Electrical Engineering (EE) Questions  >  Crashing isa)Abandoning the projectb)Completi... Start Learning for Free
Crashing is
  • a)
    Abandoning the project
  • b)
    Completing the project with all possible haste
  • c)
    Reduction of duration for a few of the activities
  • d)
    Reducing the cost of the project with all needful modifications
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
Crashing isa)Abandoning the projectb)Completing the project with all p...
Crashing is the method for shortening the project duration by reducing the time of one or more critical activities to less than their normal time. In crashing if cost increases then time decreases.
Free Test
Community Answer
Crashing isa)Abandoning the projectb)Completing the project with all p...
Crashing in Project Management
Crashing in project management refers to the technique of reducing the project's duration by adding more resources to critical path activities. This is done to complete the project in a shorter time frame than originally planned.

Explanation

Reduction of duration for a few of the activities:
- Crashing involves identifying critical path activities that are causing delays in the project schedule.
- By adding more resources to these critical activities, their duration can be reduced, ultimately shortening the overall project duration.
- This allows for the project to be completed with all possible haste without abandoning the project or compromising on quality.

Benefits of Crashing
- Completing the project in a shorter time frame
- Meeting tight deadlines
- Minimizing project delays
- Improving overall project efficiency
In conclusion, crashing involves reducing the duration of critical path activities to speed up project completion without compromising on quality. This technique is often used in project management to meet tight deadlines and ensure project success.
Explore Courses for Electrical Engineering (EE) exam
Question Description
Crashing isa)Abandoning the projectb)Completing the project with all possible hastec)Reduction of duration for a few of the activitiesd)Reducing the cost of the project with all needful modificationsCorrect answer is option 'C'. Can you explain this answer? for Electrical Engineering (EE) 2026 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about Crashing isa)Abandoning the projectb)Completing the project with all possible hastec)Reduction of duration for a few of the activitiesd)Reducing the cost of the project with all needful modificationsCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2026 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Crashing isa)Abandoning the projectb)Completing the project with all possible hastec)Reduction of duration for a few of the activitiesd)Reducing the cost of the project with all needful modificationsCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Crashing isa)Abandoning the projectb)Completing the project with all possible hastec)Reduction of duration for a few of the activitiesd)Reducing the cost of the project with all needful modificationsCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of Crashing isa)Abandoning the projectb)Completing the project with all possible hastec)Reduction of duration for a few of the activitiesd)Reducing the cost of the project with all needful modificationsCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Crashing isa)Abandoning the projectb)Completing the project with all possible hastec)Reduction of duration for a few of the activitiesd)Reducing the cost of the project with all needful modificationsCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Crashing isa)Abandoning the projectb)Completing the project with all possible hastec)Reduction of duration for a few of the activitiesd)Reducing the cost of the project with all needful modificationsCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Crashing isa)Abandoning the projectb)Completing the project with all possible hastec)Reduction of duration for a few of the activitiesd)Reducing the cost of the project with all needful modificationsCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Crashing isa)Abandoning the projectb)Completing the project with all possible hastec)Reduction of duration for a few of the activitiesd)Reducing the cost of the project with all needful modificationsCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev