What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?
  • a)
    (Std. Time for Actual Output - Budgeted Time) x Std. Rate
  • b)
    (Actual Time Worked - Budgeted Time) x Std. Rate
  • c)
    (Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Day
  • d)
    (Revised Budgeted Time - Budgeted Time) x Std. Rate per Time
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
What is the formula for calculating Fixed Overhead Volume Variance (FO...
The correct formula for calculating Fixed Overhead Volume Variance (FOVV) is (Std. Time for Actual Output - Budgeted Time) x Std. Rate. FOVV measures the variance in overhead costs due to differences in the volume of output produced compared to the budgeted volume.
Explore Courses for B Com exam
What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer?
Question Description
What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer? for B Com 2024 is part of B Com preparation. The Question and answers have been prepared according to the B Com exam syllabus. Information about What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for B Com 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer?.
Solutions for What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for B Com. Download more important topics, notes, lectures and mock test series for B Com Exam by signing up for free.
Here you can find the meaning of What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice What is the formula for calculating Fixed Overhead Volume Variance (FOVV)?a)(Std. Time for Actual Output - Budgeted Time) x Std. Rateb)(Actual Time Worked - Budgeted Time) x Std. Ratec)(Actual No. of Working Days - Std. No. of Working Days) x Std. Rate per Dayd)(Revised Budgeted Time - Budgeted Time) x Std. Rate per TimeCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice B Com tests.
Explore Courses for B Com exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev