Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  If the bed level of canal and drainage work i... Start Learning for Free
If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?
  • a)
    Aqueduct
  • b)
    Super passage
  • c)
    Syphon aqueduct
  • d)
    Canal Syphon
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
If the bed level of canal and drainage work is given as 124m and 130m ...
  • Aqueduct: To carry the canal over a natural drain. It is adopted where the bed level of the canal is well above the high flood level of drain.
  • Syphon Aqueduct: Is constructed where the water surface level of the drain at high flood is higher than the canal bed. The bed of drain is depressed and provided with a pucca floor
  • Super passage: To carry natural drain over the canal. Constructed where the bed of drain is well above the canal FSL.
  • Canal Syphon: Constructed where the full supply level (FSL) of the canal is higher than the bed of the drain. Here bed of the canal is depressed.
    Since FSL = 124 + 12 = 136 m
    HFL = 130 + 0.7 = 130.7 m
    Therefore FSL> drainage bed level. Canal Syphon should be provided.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer?
Question Description
If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer?.
Solutions for If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If the bed level of canal and drainage work is given as 124m and 130m respectively and the depth of flow of canal and drainage 12m and 0.7m respectively. Which of the following type of cross-drainage should be recommended?a)Aqueductb)Super passagec)Syphon aqueductd)Canal SyphonCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev