If 6 trucks can transport 480 tons of goods in 4 days, how many tons o...
Given information:
- Number of trucks = 6
- Amount of goods transported = 480 tons
- Number of days taken = 4
Finding:
- Amount of goods transported by 9 trucks in 6 days
Solution:
To find the amount of goods transported by 9 trucks in 6 days, we can use the concept of "work" and assume that the rate of work for each truck is the same.
Step 1: Calculate the rate of work per truck per day
The rate of work for 6 trucks in 4 days can be calculated by dividing the total amount of goods transported by the number of trucks and the number of days:
Rate of work per truck per day = Amount of goods transported / (Number of trucks * Number of days)
Rate of work per truck per day = 480 tons / (6 trucks * 4 days)
Rate of work per truck per day = 20 tons
Step 2: Calculate the total work done by 9 trucks in 6 days
To find the total work done by 9 trucks in 6 days, we need to multiply the rate of work per truck per day by the number of trucks and the number of days:
Total work done = Rate of work per truck per day * (Number of trucks * Number of days)
Total work done = 20 tons * (9 trucks * 6 days)
Total work done = 20 tons * 54
Total work done = 1080 tons
Step 3: Conclusion
Therefore, 9 trucks can transport 1080 tons of goods in 6 days, assuming they work at the same rate.