As per IS specifications, the maximum final setting time for ordinary Portland cement should be
  • a)
    30 minutes
  • b)
    1 hour
  • c)
    6 hour
  • d)
    10 hours
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
As per IS specifications, the maximum final setting time for ordinary ...
Explanation:


  • Final Setting Time: Final setting time is the time taken by cement to harden and achieve its final setting state.

  • IS Specifications: The Indian Standard specifications for ordinary Portland cement specify the maximum final setting time.

  • Maximum Final Setting Time: According to IS specifications, the maximum final setting time for ordinary Portland cement should be 10 hours.

  • Options:

    • A: 30 minutes - This is incorrect as the maximum final setting time is 10 hours.

    • B: 1 hour - This is incorrect as the maximum final setting time is 10 hours.

    • C: 6 hours - This is incorrect as the maximum final setting time is 10 hours.

    • D: 10 hours - This is the correct option according to IS specifications.



Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer?
Question Description
As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer?.
Solutions for As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice As per IS specifications, the maximum final setting time for ordinary Portland cement should bea)30 minutesb)1 hourc)6 hourd)10 hoursCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev