A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In how many days is the work done?
  • a)
    15 days
  • b)
     14 days
  • c)
    13 days 
  • d)
     11 days
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
A, B and C can do a piece of work in 24, 30 and 40 days respectively. ...
Calculation:

Step 1: Find the combined work rate of A, B, and C
Given:
A takes 24 days to complete the work, so A's work rate = 1/24
B takes 30 days to complete the work, so B's work rate = 1/30
C takes 40 days to complete the work, so C's work rate = 1/40
Combined work rate of A, B, and C = 1/24 + 1/30 + 1/40
= 5/120 + 4/120 + 3/120
= 12/120
= 1/10
Therefore, A, B, and C together can complete 1/10 of the work in 1 day.

Step 2: Calculate the total number of days taken to complete the work
Let the total number of days taken to complete the work be x days.
Since A, B, and C together can complete 1/10 of the work in 1 day, in x days, they can complete x/10 of the work.
Given that C leaves 4 days before the completion of the work, the remaining work is 1 - x/10 = (10 - x)/10
Since A and B are still working together, their combined work rate is 1/24 + 1/30 = 7/120
Therefore, (10 - x)/10 = (7/120) * (x-4)
Solving the above equation:
(10 - x)/10 = (7/120) * (x-4)
120(10 - x) = 7(x-4) * 10
1200 - 120x = 70x - 280
1200 + 280 = 70x + 120x
1480 = 190x
x = 1480/190
x = 7.79
Therefore, the work is done in approximately 8 days, which is closest to 11 days (option D).
Attention Interview Preparation Students!
To make sure you are not studying endlessly, EduRev has designed Interview Preparation study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Interview Preparation.
Explore Courses for Interview Preparation exam

Top Courses for Interview Preparation

A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer?
Question Description
A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer? for Interview Preparation 2024 is part of Interview Preparation preparation. The Question and answers have been prepared according to the Interview Preparation exam syllabus. Information about A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Interview Preparation 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer?.
Solutions for A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Interview Preparation. Download more important topics, notes, lectures and mock test series for Interview Preparation Exam by signing up for free.
Here you can find the meaning of A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In howmany days is the work done?a)15 daysb)14 daysc)13 daysd)11 daysCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Interview Preparation tests.
Explore Courses for Interview Preparation exam

Top Courses for Interview Preparation

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev