Consider the PERT network shown  below:
The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.
  • a)
    3 Weeks 
  • b)
    38 Weeks 
  • c)
    35 Weeks 
  • d)
    30 Weeks 
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
Consider the PERT network shown below:The desired completion date for ...
Critical path
    A - B - D - F - G
    Project time = 38
TS = 35 Weeks
View all questions of this test
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer?
Question Description
Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the PERT network shown below:The desired completion date for the project if probability of finishing the project is 19% (Z(0.87) = 0.19) is.a)3 Weeksb)38 Weeksc)35 Weeksd)30 WeeksCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev