Match List-I (contract types) with List-II (Characteristics):
List-I
a. Labour contract
b.Item rate contract
c. Piecework contract
d.Lump sum contract
List-II
1.Petty works and regular maintenance work
2.Adopted for buildings, roads, bridges and electrical works
3.Payment made by detailed measurement of different time
4.Not practiced in government
  • a)
    a-3,b-4,c- 2,d -1
  • b)
    a-4,b-3,c-2,d-1
  • c)
    a-3,b-4,c-1,d-2
  • d)
    a-4,b-3,c-1,d-2
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
Match List-I (contract types) with List-II (Characteristics):List-Ia. ...
Labour Contract- Workers who are hired for a specific task and a finite period.
Item Rate Contract- Contractor gets paid on ‘per item basis’-Payment by detailed measurement of different time.
Piecework Contract- Paying contractor pay rate for each unit/ work they produce/accomplish-Petty works and regular maintenance work
Lump sum Contract-A single lump sum price for all works is agreed before works begin. Adopted for buildings, roads, bridges and electrical works.
View all questions of this test
Most Upvoted Answer
Match List-I (contract types) with List-II (Characteristics):List-Ia. ...
List-I:

a. Labour contract
b. Item rate contract
c. Piecework contract
d. Lump sum contract

List-II:

1. Petty works and regular maintenance work
2. Adopted for buildings, roads, bridges, and electrical works
3. Payment made by detailed measurement of different time
4. Not practiced in the government

Explanation:

Labour Contract:

- This type of contract is used for unskilled and semi-skilled workers.
- Wages are paid on a daily or weekly basis.
- The contractor is responsible for providing all the necessary tools and equipment.

Item Rate Contract:

- This type of contract is commonly used in the construction industry.
- The payment is made based on the rates of various items in the bill of quantities.
- The contractor is responsible for providing all the necessary materials, labor, and equipment.

Piecework Contract:

- In this type of contract, payment is made based on the number of units produced.
- This type of contract is used for skilled workers who can produce a certain number of units in a given time.
- The contractor is responsible for providing all the necessary tools and equipment.

Lump Sum Contract:

- In this type of contract, a fixed amount is agreed upon for the entire project.
- The contractor is responsible for completing the project within the agreed time and budget.
- Any additional work or changes to the project scope are negotiated separately.

Conclusion:

In summary, the different types of contracts have their own unique characteristics and are used for different types of projects. It is important to choose the right type of contract depending on the project requirements and budget.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer?
Question Description
Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer?.
Solutions for Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Match List-I (contract types) with List-II (Characteristics):List-Ia. Labour contractb.Item rate contractc. Piecework contractd.Lump sum contractList-II1.Petty works and regular maintenance work2.Adopted for buildings, roads, bridges and electrical works3.Payment made by detailed measurement of different time4.Not practiced in governmenta)a-3,b-4,c- 2,d -1b)a-4,b-3,c-2,d-1c)a-3,b-4,c-1,d-2d)a-4,b-3,c-1,d-2Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev