Question 1: The network of a small construction project awarded to a contractors is shown in the following figure. The normal duration, crash duration, normal cost and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor in I NR 5000 per day.    [2019 : 2 Marks, Set-1]
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
If the project is target for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be_______.

Solution:
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)

Considering normal durations, the total cost of the project
TC = DC + IC
= INR 66000 + INR 5000 x 18
= INR 156000
Stage-I: Crash activity R by 1 day
∴ Project becomes
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
TC = (INR 6600 + INR 750) + INR 5000 x 17
= 151750
Stage-II: Crash activity Q&R (or U&R) by 1 day
∴ Project becomes
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
TC = (INR 66750 + INR 2000 + INR 750) + (INR 5000 x 16)
= 149500

Question 2: For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate, z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be _____.     [2017 :1 Mark, Set-II]
Solution: Expected completion time of project,

Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)

Question 3: Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred?    [2017 : 1 Mark, Set-II]
(a) EPC contract 
(b) Percentage rate contract 
(c) Item rate contract 
(d) Lump sum contract
Answer: (c)
Solution: Percentage rate Contract: In this form of contract, the displacemente draws up 'Item rate tender' i.e., bill of quantities with-rate, amount and total amount. The contractors are required to offer to carry out the work as per the rates shown in the specifi price schedule or some percenrage above or some percentage below the rates indicated in the shedule of work attached with the tender.
Item rate contract: In this a contract under takes the execution of work on an item rate basis. He is required to quote rate for individual item of work o the basis of shedule of quantities i.e., BOQ furnished by the department.
Lumpsum concract: In this type, a contractor is required to quote a fixed sum for execution of work complete in all respect in the stipulated time according to the drawing, design and specification supportd to him with the tender. In item rate contract, contractor only fill its rate against given item and its quantity and contract does not change the item make, drawing, specification during construction without consent of owner/department.
Item rate contract is also called “unit price contract” where contractor bids cost per unit of each item. These works are carried out in accordance with contract documents. The contractor has to perform the quantities of the work actually required in the field at his quoted unit prices, whether they are less or greater than “owner/department” estimates.

Question 4: The activity details of a project are given below:    [2017 : 2 Marks, Set-I]
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
The estimated minimum time (in days) for the completion of the project will be _____ .
Solution:
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
Note: Path of longest duration is defined as the critical path as the activities lying in this path are called critical activities. Any delay in these activity will lead to delay in overall project. The project time given by critical path. Hence the time taken by the critical path is the shortest possible time to finish the project.
Critical Path → P - Q - U - V
Tcp = 6 + 15 + 14 + 16 = 51 days

Question 5: The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below the arrows.    [2016 : 2 Marks, Set-II
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
The critical duration for this construction project is
(a) 13 days 
(b) 14 days 
(c) 15 days 
(d) 16 days
Answer: (c)
Solution: 
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
The critical duration is 15 days which is observed along the path P-Q-T-W-X which is the critical path of the project.
Note: Critical path is the one which consumes maximum amount of time.

Question 6: The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.   [2016 : 2 Marks, Set-I]
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
The expected completion time (in days) of the project is __________
Solution:
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)

Question 7: A construction project consists of twelve activities The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.    [2016 : 1 Mark, Set-II]
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively, 
(a) 25 and 1 
(b) 1 and 1 
(c) 0 and 0 
(d) 81 and 0
Answer: (c)
Solution: Total float can be determined once the activity times i.e. EST, EFT, LST and LFT are known.
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
For activity 5-7,
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
For activity 11-12,
Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)
Note: It can be seen directly that since the slack of all events are zero, there is not margin left for the occurence of events and therefore.
Maximum available line = Time required for completion of activity
∴ FT for all activities is zero.

The document Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE) is a part of the Civil Engineering (CE) Course Construction Materials & Management.
All you need of Civil Engineering (CE) at this link: Civil Engineering (CE)
Are you preparing for Civil Engineering (CE) Exam? Then you should check out the best video lectures, notes, free mock test series, crash course and much more provided by EduRev. You also get your detailed analysis and report cards along with 24x7 doubt solving for you to excel in Civil Engineering (CE) exam. So join EduRev now and revolutionise the way you learn!
Sign up for Free Download App for Free
5 videos|21 docs|16 tests

Up next

FAQs on Past Year Questions: Construction Management - Construction Materials & Management - Civil Engineering (CE)

1. What is construction management?
2. What are the key responsibilities of a construction manager?
Ans. A construction manager is responsible for a wide range of tasks, including project planning, budgeting, scheduling, coordinating subcontractors, managing resources, ensuring safety compliance, and resolving any issues or conflicts that may arise during construction.
3. How can construction managers ensure project success?
Ans. Construction managers can ensure project success by effectively managing the project timeline, closely monitoring and controlling costs, maintaining clear communication with all stakeholders, conducting regular inspections to ensure quality standards are met, and proactively addressing any potential risks or issues.
4. What challenges do construction managers commonly face?
Ans. Construction managers commonly face challenges such as unexpected delays, changes in project scope, managing multiple subcontractors, ensuring compliance with building codes and regulations, and dealing with unforeseen problems that may arise during construction.
5. What skills are essential for a successful construction manager?
Ans. Essential skills for a successful construction manager include strong leadership and communication skills, excellent problem-solving abilities, knowledge of construction methods and materials, proficiency in project management software, financial management skills, and the ability to work well under pressure and meet deadlines.
5 videos|21 docs|16 tests
Download as PDF

Up next

Explore Courses for Civil Engineering (CE) exam
Related Searches

study material

,

Extra Questions

,

Semester Notes

,

video lectures

,

Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)

,

MCQs

,

Objective type Questions

,

practice quizzes

,

Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)

,

pdf

,

Viva Questions

,

Sample Paper

,

shortcuts and tricks

,

Free

,

Past Year Questions: Construction Management | Construction Materials & Management - Civil Engineering (CE)

,