Past Year Questions: Production Planning Mechanical Engineering Notes | EduRev

Manufacturing and Industrial Engineering

Mechanical Engineering : Past Year Questions: Production Planning Mechanical Engineering Notes | EduRev

The document Past Year Questions: Production Planning Mechanical Engineering Notes | EduRev is a part of the Mechanical Engineering Course Manufacturing and Industrial Engineering.
All you need of Mechanical Engineering at this link: Mechanical Engineering

Question 1:Cylindrical pins of diameter 15±0.020 mm are being produced on a machine. Statistical quality control tests show a mean of 14.995 mm and standard deviation of 0.004 mm. The process capability index Cp is

[2017]

Question 2:During the development of a product, an entirely new process plan is made based on design logic, examination of geometry and tolerance information. This type of process planning is known as

[2015]

Question 3:Which one of the following is NOT a decision taken during the aggregate production planning stage?

[2012]

Question 4:The word kanban is most appropriately associated with

[2011 : 1 Mark]

Question 5:Vehicle manufacturing assembly line is an example of

[2010]

Question 6:The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:​Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is
Past Year Questions: Production Planning Mechanical Engineering Notes | EduRev

[2008]

Question 7:Capacities of production of an item over 3 consecutive months in regular time are 100,100 and 80 and in overtime are 20, 20 and 40. The demands over those 3 months are 90, 130 and 110. The cost of production in regular time and overtime are respectively Rs. 20 per item and Rs. 24 per item. Inventory carrying cost is Rs. 2 per item month. The levels of starting and final inventory are nil. Backorder is not permitted. For minimum cost of plan, the level of planned production in overtime in the third month is

[2007]

Question 8:The table gives details of an assembly line.​What is the line efficiency of the assembly line?
Past Year Questions: Production Planning Mechanical Engineering Notes | EduRev

[2006]

Question 9:A manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is​The optimal make-span (in hours) of the shop is

[2006]

Question 10:A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is

[2005]

Question 11:An electronic equipment manufacturer has decided to add a component subassembly operation that can produce 80 units during a regular 8-hour shift.This operation consists of three activities as below​For line balancing the number of work stations required for the activities M, E and T would respectively be

[2004]

Question 12:A soldering operation was work-sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of the total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would be

[2004]

Question 13:A standard machine tool and an automatic machine tool are being compared for the production of a component. Following data refers to the two machines.​The breakeven production batch size above which the automatic machine tool will be economical to use, will be

[2004]

Question 14:Two machines of the same production rate are available for use. On machine 1, the fixed cost is Rs. 100 and the variable cost is Rs. 2 per piece produced. The corresponding numbers for the machine are Rs. 200 and Rs. 1 respectively.For certain strategic reasons both the machines are to be used concurrently. The sale price of the first 800 units is Rs. 3.50 per unit & and subsequently it is only Rs. 3.00. The breakeven production rate for each machine is

[2003]

Question 15:Production flow analysis (PFA) is a method of identifying part families that uses data from

[2001]

Question 16:The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is

[1995]


Offer running on EduRev: Apply code STAYHOME200 to get INR 200 off on our premium plan EduRev Infinity!

Related Searches

Extra Questions

,

Previous Year Questions with Solutions

,

Important questions

,

Free

,

Summary

,

mock tests for examination

,

Objective type Questions

,

Viva Questions

,

past year papers

,

Sample Paper

,

pdf

,

Past Year Questions: Production Planning Mechanical Engineering Notes | EduRev

,

Semester Notes

,

ppt

,

Exam

,

shortcuts and tricks

,

MCQs

,

Past Year Questions: Production Planning Mechanical Engineering Notes | EduRev

,

study material

,

practice quizzes

,

video lectures

,

Past Year Questions: Production Planning Mechanical Engineering Notes | EduRev

;