Civil Engineering (CE) Exam  >  Civil Engineering (CE) Notes  >  Foundation Engineering  >  Piles & Settlement of Piles Group

Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE) PDF Download

Design Methodology for Piles
The detailed design methodology of piles is described in the following sections.

Requirement for Deep Foundations
Generally for structures with load >10 , we go for deep foundations. Deep foundations are used in the following cases:
• Huge vertical load with respect to soil capacity.
• Very weak soil or problematic soil.
• Huge lateral loads eg. Tower, chimneys.
• Scour depth criteria.
• For fills having very large depth.
• Uplift situations (expansive zones)
• Urban areas for future large and huge construction near the existing building.

Classification of  Piles
1. 
Based on material 
• Timber piles
• Steel piles
• Concrete piles
• Composite piles (steel + concrete)
2. Based on method of installation 
• Driven piles ----(i) precast (ii) castin-situ.
•Bored piles.
3. Based on the degree of disturbance 
• Large displacement piles (occurs for driven piles)
• Small displacement piles (occurs for bored piles)

Points to be Considered for Chossing Piles 
• Loose cohesion less soil develops much greater shaft bearing capacities if driven large displacement piles are used.
• Displacement effect enhanced by tapered shafts.
•Potential increased of shaft capacities is undesirable if negative friction is to be feared. (Negative friction is also called drag down force)
• High displacement piles are undesirable in stiff cohesive soils, otherwise excessive heaving takes place.
• Encountered with high artesian pressures on cased piles should be excluded. (Mainly for bridges and underwater construction)
• Driven piles are undesirable due to noise, damage caused by vibration, ground heaving.
• Heavy structures with large reactions require high capacity piles and small diameter cast-in-situ piles are inadequate.

Pile Classification 
• Friction piles.
• End bearing piles.
• Compaction piles.( Used for ground movement, not for load bearing )
• Tension piles/Anchored piles.(To resist upliftment) 
• Butter piles (Inclined) --- +ve and –ve.
Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)
Fig. 5.1 Direction of load is same as the direction of batter. (Rotation of pile)

Raymond piles. (Driven cast-in-situ piles, first tapered shell is driven and then cast) Franki Piles (Driven cast-in-situ piles, first casing is driven upto 2m depth, then cast a block within that casing and then drive the block. When it reaches the particular depth, take out the casing and cast the piles.) Underreamed piles (bored cast-in-situ piles, bulbs used, hence not possible to install in loose sand and very soft clays.)
Piles in Clay Zone of influence
Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)

The heaving effect can be felt upto (10 –15) D from the centerline of the pile. Due to driving load, pressure is generated and as a result heaving occurs. Afterwards with time, the heaved part gets consolidated and strength gradually increases as the material regains shear strength within 3 – 6 months time after the installation of the pile. This regain of strength is called thixotrophy.
On the first day some part of the pile will be driven and on the second day some part of the pile may move up due to the gain of shear strength. This is known as the wakening of the pile. By the driving force, the extra pore pressure generated is (5 – 7) times the Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE) of the soil. Bearing capacity of the pile is 9 Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE) . Hence due to this property, maximum single length of the pile theoretically can be upto 25m but 10- 12m is cast at a time. Then by splicing technique the required hired length of the pile is obtained. Special types of collars are used so that the splices become weak points. Concrete below the grade M20 is never used.
Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)

Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)
Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)
                   Fig.5.3 Generation of
             Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)
 

Piles in Sand 
Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)
     Fig.5.4a Driven piles in loose sand
Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)
 Fig.5.4b Improvement in f due to pile driving

Settlement of Piles Group
Assume 2V:1H dispersion for settlement of pile groups.
Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)
     Fig.5.5 Settlement of pile groups

Codal Provison Safe Load on Piles /Pile Groups ( Ref. IS: 2911 Part IV 1979 ) Single pile: 1. Safe load = Least of the following loads obtained from routine tests on piles : 2/3 of the final load at which total settlement is 12mm. 50% of the final load at which settlement is 10% of the pile dia.( for uniform dia. piles) and 7.5% of bulb dia. (for Underreamed piles) 2/3 of the final load at which net settlement is 6mm. 
Consider pile as column and find the total compressive load depending on the grade of concrete and dimensions. Eg. Consider a 300mm dia pile made of M20 concrete  Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)

Therefore, ultimate load = Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)
.                                   Fig 5.40 Multiple Under Reamed Pile

Under reamed piles are bored cast-in-situ concrete piles having one or more number of bulbs formed by enlarging the pile stem. These piles are best suited in soils where considerable ground movements occur due to seasonal variations, filled up grounds or in soft soil strata. Provision of under reamed bulbs has the advantage of increasing the bearing and uplift capacities. It also provides better anchorage at greater depths. These piles are efficiently used in machine foundations, over bridges, electrical transmission tower foundation sand water tanks. Indian Standard IS 2911 (Part III) - 1980 covers the design and construction of under reamed piles having one or more bulbs. According to the code the diameter of under reamed bulbs may vary from 2 to 3 times the stem diameter depending upon the feasibility of construction and design requirements. The code suggests a spacing of 1.25 to 1.5 times the bulb diameter for the bulbs. An angle of 45 0 with horizontal is recommended for all under reamed bulbs. This code also gives Mathematical expressions for calculating the bearing and uplift capacities.
From the review of the studies pertaining to under reamed piles, it can be seen that ultimate bearing capacity of piles increases considerably on provision of underreamed bulbs (Neumann and P&g, 1955, Subash Chandra and Kheppar, 1964, Patnakar, 1970 etc.). Pile load capacity was found to vary with the number of bulbs and with the spacing ratio S / Du or S/d adopted (where S = distance between the piles, Du = diameter of under reamed bulbs and d = diameter of piles). Table summarizes the various recommendations made for the selection of S / Du and S/d for the optimum pile load capacity. It can be seen that some of these recommendations differ from those given in IS 2911 (Part III), 1980.

Table: 5.6 of recommendations for S / Dand S/d for the optimum pile load capacity
Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)
Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)

The choice of an under-reamed pile in unstable or water-bearing ground is generally to be avoided. There is a danger of collapse of the under-ream, either when personnel are down the hole, or during concreting.
Important Notes: On the basis of limited experimental studies conducted on model under reamed piles in cohesion less soil the following conclusions are drawn.
1. By providing under reamed bulbs the ultimate load capacities of piles increases significantly.
2. The ultimate load bearing capacities of the under reamed piles with angle of under reamed bulbs of 450 and zero are almost same.
3. Three or more under reamed bulbs are advantageous only when the spacing ratio (S / Du ) is ) is two or less, and when (S / Du ) is greater than two, multi-under reamed piles do not have specific advantages.
4. The ultimate load bearing capacities of piles are maximum when the spacing between two under reamed bulb is 2.5 times the diameter of the under reamed bulb. It appears that the spacing between two under reamed bulbs suggested in (1.25 to 1.5 times) IS 2911(1980) is not the optimum,
5. The expression suggested in IS 2911(1980) can be used for predicting the ultimate load carrying capacity of under reamed piles with spacing ratio (S / Du) less than. 

The document Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE) is a part of the Civil Engineering (CE) Course Foundation Engineering.
All you need of Civil Engineering (CE) at this link: Civil Engineering (CE)
18 videos|46 docs|27 tests

Top Courses for Civil Engineering (CE)

FAQs on Piles & Settlement of Piles Group - Foundation Engineering - Civil Engineering (CE)

1. What are piles in civil engineering?
Ans. Piles are long cylindrical structures made of concrete, steel, or timber that are driven or drilled into the ground to provide support to structures like buildings, bridges, and retaining walls. They transfer the load from the structure to a stronger layer of soil or rock beneath the ground.
2. How are piles installed?
Ans. Piles can be installed in different ways depending on the type of soil and the load-bearing capacity required. Common methods include driving piles into the ground using a pile driver, drilling holes and then placing the piles inside, or using precast piles that are simply lowered into position. The choice of installation method depends on factors such as soil conditions, accessibility, and project requirements.
3. What is settlement of piles and why is it important?
Ans. Settlement of piles refers to the vertical movement or sinking of piles after they have been installed. It occurs due to factors such as soil compression, consolidation, or deformation. Settlement is an important consideration in pile design and construction as excessive settlement can lead to structural damage, stability issues, or reduced load-bearing capacity.
4. What are the different types of settlement of piles?
Ans. There are two main types of settlement associated with piles: immediate settlement and long-term settlement. Immediate settlement occurs immediately after the installation of piles due to soil compression and displacement. Long-term settlement, on the other hand, happens over an extended period of time due to factors such as soil consolidation or creep. Both types of settlement need to be carefully considered in the design and construction of pile foundations.
5. How is settlement of piles controlled or minimized?
Ans. Settlement of piles can be controlled or minimized through various measures. These include conducting thorough site investigations to understand the soil conditions, selecting appropriate pile types and installation methods, using proper construction techniques, and considering soil improvement methods such as compaction or stabilization. Additionally, monitoring and regular maintenance of pile foundations can help detect and address any settlement issues before they become significant problems.
18 videos|46 docs|27 tests
Download as PDF
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev
Related Searches

MCQs

,

Important questions

,

Exam

,

Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)

,

practice quizzes

,

mock tests for examination

,

past year papers

,

study material

,

Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)

,

video lectures

,

Previous Year Questions with Solutions

,

pdf

,

Piles & Settlement of Piles Group | Foundation Engineering - Civil Engineering (CE)

,

Objective type Questions

,

Extra Questions

,

ppt

,

Sample Paper

,

Semester Notes

,

Summary

,

shortcuts and tricks

,

Free

,

Viva Questions

;