CAT Exam  >  CAT Notes  >  Topic-wise Past Year Questions for CAT  >  CAT Previous Year Questions: Time & Work

Time & Work CAT Previous Year Questions with Answer PDF

*Answer can only contain numeric values
Question for CAT Previous Year Questions: Time & Work
Try yourself:The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression. Kamal takes twice as much time as Amal to do the same amount of job. If Amal and Sunil work for 4 days and 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job. Then the number of days Sunil will take to finish the job working alone, is

[2023]

Check
View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:Rahul, Rakshita and Gurmeet, working together, would have taken more than 7 days to finish a job. On the other hand, Rahul and Gurmeet, working together would have taken less than 15 days to finish the job. However, they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job. If Rakshita had worked alone on the job then the number of days she would have taken to finish the job, cannot be

[2023]

View Solution

*Answer can only contain numeric values
Question for CAT Previous Year Questions: Time & Work
Try yourself:Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is

[2022]

Check
View Solution

*Answer can only contain numeric values
Question for CAT Previous Year Questions: Time & Work
Try yourself:Bob can finish a job in 40 days, if he works alone. Alex is twice as fast as Bob and thrice as fast as Cole in the same job. Suppose Alex and Bob work together on the first day, Bob and Cole work together on the second day, Cole and Alex work together on the third day, and then, they continue the work by repeating this three - day roster, with Alex and Bob working together on the fourth day, and so on. Then, the total number of days Alex would have worked when the job gets finished, is

[2022]

Check
View Solution

*Answer can only contain numeric values
Question for CAT Previous Year Questions: Time & Work
Try yourself:Amar, Akbar and Anthony are working on a project. Working together Amar and Akbar can complete the project in 1 year, Akbar and Anthony can complete in 16 months, Anthony and Amar can complete in 2 years. If the person who is neither the fastest nor the slowest works alone, the time in months he will take to complete the project is   
                                                                                                                                                                                             [2021]
Check
View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:Anu, Vinu and Manu can complete a work alone in 15 days, 12 days and 20 days, respectively. Vinu works everyday. Anu works only on alternate days starting from the first day while Manu works only on alternate days starting from the second day. Then, the number of days needed to complete the work is    [2021]
View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:Anil can paint a house in 60 days while Bimal can paint it in 84 days. Anil starts painting and after 10 days, Bimal and Charu join him. Together, they complete the painting in 14 more days. If they are paid a total of ₹ 21000 for the job, then the share of Charu, in INR, proportionate to the work done by him, is   
                                                                                                                                                                                            [2021]
View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:One day, Rahul started a work at 9 AM and Gautam joined him two hours later. They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is    [2021]
View Solution

*Answer can only contain numeric values
Question for CAT Previous Year Questions: Time & Work
Try yourself:Anil can paint a house in 12 days while Barun can paint it in 16 days. Anil, Barun, and Chandu undertake to paint the house for ₹ 24000 and the three of them together complete the painting in 6 days. If Chandu is paid in proportion to the work done by him, then the amount in INR received by him is   [2021]
Check
View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:At their usual efficiency levels, A and B together finish a task in 12 days. If A had worked half as efficiently as she usually does, and B had worked thrice as efficiently as he usually does, the task would have been completed in 9 days. How many days would A take to finish the task if she works alone at her usual efficiency?

[2019]

View Solution


Question for CAT Previous Year Questions: Time & Work
Try yourself:Anil alone can do a job in 20 days while Sunil alone can do it in 40 days. Anil starts the job, and after 3 days, Sunil joins him. Again, after a few more days, Bimal joins them and they together finish the job, If Bimal has done 10% of the job, then in how many days was the job done?

[2019]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:A tank is fitted with pipes, some filling it and the rest draining it. All filling pipes fill at the same rate, and all draining pipes drain at the same rate. The empty tank gets completely filled in 6 hours when 6 filling and 5 draining pipes are on, but this time becomes 60 hours when 5 filling and 6 draining pipes are on. In how many hours will the empty tank get completely filled when one draining and two filling pipes are on?

[2018]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:Humans and robots can both perform a job but at different efficiencies. Fifteen humans and five robots working together take thirty days to finish the job, whereas five humans and fifteen robots working together take sixty days to finish it. How many days will fifteen humans working together (without any robot) take to finish it?

[2018]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:When they work alone, B needs 25% more time to finish a job than A does. The two finish the job in 13 days in the following manner : A works alone till half the job is done, then A and B work together for four days, and finally B works alone to complete the remaining 5% of the job. In how many days can B alone finish the entire job?

[2018]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:A tank is emptied everyday at a fixed time point, Immediately thereafter, either pump A or pump B or both start working until the tank is full. On Monday, A alone completed filling the tank at 8 pm. On Tuesday, B alone completed filling the tank at 6 pm. On Wednesday, A alone worked till 5 pm, and then B worked alone from 5 pm to 7 pm, to fill the tank. At what time was the tank filled on Thursday if both pumps were used simultaneously all along?

[2018]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:A water tank has inlets of two types A and B. All inlets of type A when open, bring in water at the same rate. All inlets of type B, when open, bring in water at the same rate. The empty tank is completely filled in 30 minutes if 10 inlets of type A and 45 inlets of type B are open, and in 1 hour if 8 inlets of type A and 18 inlets of type B are open. In how many minutes will the empty tank get completely filled if 7 inlets of type A and 27 inlets of type B are open?

[2018]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?

[2018]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:A person can complete a job in 120 days. He works alone on Day 1. On Day 2, he is joined by another person who also can complete the job in exactly 120 days. On Day 3, they are joined by another person of equal efficiency. Like this, everyday a new person with the same efficiency joins the work. How many days are required to complete the job?

[2017]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:A tank has an inlet pipe and an outlet pipe. If the outlet pipe is closed, then the inlet pipe fills the empty tank in 8 hours. If the outlet pipe is open, then the inlet pipe fills the empty tank in 10 hours. If only the outlet pipe is open, then in how many hours the full tank becomes half-full?

[2017]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:Amal can complete a job in 10 days and Bimal can complete it in 8 days. Amal, Bimal and Kamal together complete the job in 4 days and are paid a total amount of Rs. 1000 as remuneration. If this amount is shared by them in proportion to their work, then Kamal's share, in rupees, is

[2017]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:A person can complete a job in 120 days. He works alone on Day 1. On Day 2, he is joined by another person who also can complete the job in exactly 120 days. On Day 3, they are joined by another person of equal efficiency. Like this, everyday a new person with the same efficiency joins the work. How many days are required to complete the job?

[2017]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:Four two-way pipes, A,B,C and D can either fill an empty tank or drain the full tank in 4, 10, 12 and 20 minutes, respectively. All four pipes were opened simultaneously when the tank is empty. Under which of the following conditions, the tank would be half filled after 30 minutes?

[2017]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:A water tank has M inlet pipes and N outlet pipes. An inlet pipe can fill the tank in 8 hours while an outlet pipe can empty the full tank in 12 hours. If all pipes are left open simultaneously, it takes 6 hours to fill the empty tank. What is the relationship between M and N?

[2016]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:In the marketing management course of an MBA programme, you and your roommate can complete an assignment in 30 days. If you are twice as efficient as your roommate, the time required by each to complete the assignment individually is

[2016]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:Three pipes are connected to an inverted cone, with its base at the top. Two inlet pipes, A and B, are connected to the top of the cone and can fill the empty cone in 8 hours and 12 hours, respectively. The outlet pipe C, connected to the bottom, can empty a filled cone in 4 hours. When the cone is completely filled with water, all three pipes are opened. Two of the three pipes remain open for 20 hours continuously and the third pipe remains open for a lesser time. As a result, the height of the water inside the cone comes down to 50%. Which of the following options would be possible?

[2015]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:A tank is connected with both inlet pipes and outlet pipes. Individually, an inlet pipe can fill the tank in 7 hours and an outlet pipe can empty it in 5 hours. If all the pipes are kept open, it takes exactly 7 hours for a completely filled-in tank to empty. If the total number of pipes connected to the tank is 11, how many of these are inlet pipes?

[2015]

View Solution

Question for CAT Previous Year Questions: Time & Work
Try yourself:Three carpenters P,Q and R are entrusted with office furniture work. P can do a job in 42 days. If Q is 26% more efficient than P, and R is 50% more efficient than Q, then Q and R together can finish the job in approximately:

[2015]

View Solution

The document Time & Work CAT Previous Year Questions with Answer PDF is a part of the CAT Course Topic-wise Past Year Questions for CAT.
All you need of CAT at this link: CAT
43 docs|31 tests

Top Courses for CAT

FAQs on Time & Work CAT Previous Year Questions with Answer PDF

1. How to solve time and work problems quickly?
Ans. To solve time and work problems quickly, one can use the concept of efficiency. Efficiency is calculated as work done per unit of time. By calculating the efficiency of each worker or machine involved in the work, one can easily determine the total time taken to complete the work.
2. What is the formula for calculating work done?
Ans. The formula for calculating work done is Work = Rate x Time. This formula is used to find the total amount of work completed by a person or a machine in a certain amount of time.
3. How to solve time and work problems involving multiple people working together?
Ans. When multiple people are working together on a task, their individual efficiencies can be added up to find the total efficiency of the group. By using the total efficiency, one can calculate the total time taken to complete the work.
4. How to approach time and work problems with different work rates?
Ans. When individuals or machines have different work rates, their individual efficiencies can be calculated by dividing the work done by the time taken. By comparing the efficiencies, one can determine the relative speed at which each person or machine works.
5. Can time and work problems be solved using algebraic equations?
Ans. Yes, time and work problems can be solved using algebraic equations. By setting up equations based on the work done by each person or machine, one can solve for variables such as time or rate to find the solution to the problem.
Explore Courses for CAT exam

Top Courses for CAT

Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev
Related Searches

Summary

,

Time & Work CAT Previous Year Questions with Answer PDF

,

study material

,

pdf

,

Semester Notes

,

Exam

,

Sample Paper

,

Time & Work CAT Previous Year Questions with Answer PDF

,

Important questions

,

Previous Year Questions with Solutions

,

mock tests for examination

,

Free

,

Objective type Questions

,

Extra Questions

,

practice quizzes

,

video lectures

,

shortcuts and tricks

,

Time & Work CAT Previous Year Questions with Answer PDF

,

ppt

,

MCQs

,

past year papers

,

Viva Questions

;