Civil Engineering (CE) Exam  >  Civil Engineering (CE) Notes  >  Structures for Flow Diversion, Investigation Planning and Layout (Part - 4)

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE) PDF Download

River training works 

The river training works for barrages are required to achieve the following;

  1. Prevent out flanking of the structure
  2. Minimize cross flows through the barrage
  3. prevent flooding by the river lands upstream
  4. provide favourable curvature of flow at the head regulator from the point of sediment entry into the canal, and
  5. guide the river to flow axially through the barrage or weir  

As was seen in the section on waterway, it is necessary at many instances to narrow down and restrict the course of the river through the barrage and it is achieved by the use of the river training works. Proper alignment of guide bunds is essential to ensure satisfactory flow conditions in the vicinity of the barrage. In case of wide alluvial banks, the length and curvature at the head of the guide bunds should be kept such that the worst meander loop is kept away from either the canal embankment or the approach embankment.  If the alluvial bank is close to the barrage, the guide bunds may be connected to it by providing suitable curvature, if necessary.  If there is any out-crop of hard strata on the banks, it is advisable to tie the guide bunds to such control points. Two typical guide bund layouts are shown in Figure 11. 

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

Figure 11. Typical layouts of guide banks

The dimensions given in Figure 11 are preliminary, and model studies have to be carried out for fixation of final sizes for any particular project depending upon the prevalent site conditions. 

Crest levels of spillway and undersluice bays 

The bays of a barrage are in the shape of weirs or spillways and the crest levels of these have to be decided correctly.  Some of the bays towards the canal end of the barrage are provided with lower crest (Figure 12) in order to: 

  • Maintain a clear and well defined river channel towards the canal head regulator
  • To enable the canal to draw silt free water from surface only as much as possible  
  • To scour the silt deposited in front of the head regulator 

  Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

Figure 12. Relative shapes of under sluice bays (towards the canal end) and spillway bays of a barrage. Piers, gates and walls have not been shown.

The set of undersluice bays withlow crest elevations are separated from the set of spillway bays witha small weir hump by a long wall, called the divide wall.

The layout of a barrage and its appurtenant structures can be seen from a typical plan view shown in Figure 13.  The important components of a barrage are discussed below: 

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

FIGURE 13. A typical layout of a barrage and its appurtenant structure. This example shows canal off-taking from either end

Spillway bays 

This is the main body of the barrage for controlling the discharges and to raise the water level to the desired value to feed the canals. It is a reinforced concrete structure designed as a raft foundation supporting the weight of the gates, piers and the bridge above to prevent sinking into the sandy river bed foundation. A typical section of a spillway bay is shown in Figure 14. 

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

FIGURE 14. Typical section of spillway of a barrage

Undersluice bays

These low crested bays may be provided on only one flank or on bothflanks of the river depending upon whether canals are taking-off from one or both sides.  The width of the undersluice portion is determined on the basis of the following considerations.

  • It should be capable of passing at least double the canal discharge to ensure good scouring capacity
  • It should be capable of passing about 10 to 20 percent of the maximum flood discharge at high floods
  • It should be wide enough to keep the approach velocities sufficiently lower than critical velocities to ensure maximum settling of suspended silt load.

Undersluices are often integrated withRCC tunnels or barrels, called silt excluders, extending up to the widthof the Canal Head Regulator, as can be seen from Figure 13. These tunnels are provided in order to carry the heavier silt from a distance upstream and discharge it on the downstream, allowing relatively clear water to flow above from which the Canal Head Regulator draw its share of water.

Typical sections of undersluices with and without silt excluder tunnel are shown in Figures 15 and 16.

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

FIGURE 15. Typical section of uridersluice wilii silt excluder tunnels 

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

River –sluice bays 

River sluices are a set of sluices similar to the undersluices located in between the undersluice and spiilway bays and separated from them by means of divide walls. These are generally provided in long barrages (that is, in wide rivers) for simplifying the operation of gates during normal floods and to have better control on the river. The section of river-sluice bays would generally be similar to that of undersliuce bays without silt excluding tunnels. 

Cut-off 

Cut-offs are barriers provided below the floor of the barrage both at the upstream and the downstream ends. They may be in the form of concrete lungs or steel sheet-piles, as observed from the figures 14, 15 and 16. The cut-offs extend from one end of the barrage up to the other end (on the other bank). The purpose of providing cutoff is twofolds as explained below. 

During low-flow periods in rivers, when most of the gates are closed in order to maintain a pond level, the differential pressure head between upstream and downstream may cause uplift of river bed particles (Figure 17a). A cutoff increases the flow path and reduces the uplift pressure,  ensuring stability to the structure (Figure 17b). 

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

Figure 17. Downstream riverbed uplift and its prevention. (A) Differential pressure head causing sand uplift; (B) Cutoffs to reduce uplift pressure by increasing the seepage path.

During flood flows or some unnatural flow condition, when there is substantial scour of the downstream riverbed, the cutoffs or sheet piles protect the undermining of the structures foundation (Figure 18). 

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

Figure 18. Riverbed scour resisted by sheet pile protects the foundation barrage floor.

Pier

Piers are provided between each bay.  The gates operate through the groove provided in the piers.  Usually, there are two sets of grooves, the upstream being called the Stop Log groove and the downstream one being called the Main Gate or Service gate groove. The piers are constructed usually monolithic with the floor (raft), and extend usually from the upstream end to the downstream end solid floor of the spillway (or under sluice/river sluices), as may be observed from Figure 2B. The piers have to be high enough to hold the gates clear off the maximum flood level while making ample allowance for passing any floating debris under the raised gates. 

Divide wall

The divide wall is much like a pier and is provided between the sets of undersluice or river sluice or spill bays. The main functions of a divide wall:

  • It separates the turbulent flood waters from the pocket in front of the canal head.
  • It helps in checking parallel flow (to the axis of the barrage) which would be caused by the formation of deep channels leading from the river to the pocket in front of the sluices.

The length of the divide wall on the upstream has to be such as to keep the heavy action on the nose of the divide wall away from the upstream protection of the sluices and also to provide a deep still water pond in front of the canal head regulator.

A typical section of a divide wall is shown in Figure 19. 

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

figure 19. Typical section through a divide wall

Abutment

The abutments form the end structures of the barrage and their layout depends upon the project features and topography of the site. The lengthof the abutment is generally kept same as the lengthof the floor. The top of the abutment is fixed withadequate free board over the upstream and downstream water levels. 

Flank wall

In continuation of the abutments of the diversion structure,  flank  walls are provided bothon the upstream and downstream sides on boththe banks.  The flank  walls ensure smoothentry and exit of water and away from the diversion structure. The flank  walls laid out in a flare withvertical alignment close to the abutment and a slope of 2H:1V  or 3H:1V  on the other end,  as may be observed from the layout of the barrage shown in Figure 13.

Return wall

Return walls are generally provided at right angles to the abutment either at its end or at the flank wall portion, and extends into the banks to hold the bank or back-filling earth in place.

Guide bunds 

The requirement of narrowing down and restricting wide alluvial river courses to flow axially through the barrage necessitates the use of guide bunds, as shown in Figure 10. 

Afflux bunds

Afflux bunds are components of the diversion structures wherever necessary to protect important low lying properties adjacent to the structures from submergence due to affluxed high floods.

Silt excluding devices

As shown in the layout of a barrage (Figure 13), the silt excluding tunnels carry heavy silt  down the river below the undersluices.

Navigation Lock 

Since inland or river water navigation is economically more attractive for larger cargo,  navigation facilities can be combined withthe  barrage projects. This includes the provision of a navigation channel withnavigation locks suitably incorporated to allow passage of crafts to move from upstream to downstream and vice versa (Figure 4). 

Fish pass 

Some barrages require providing special structures to allow migratory fishes to flow up and down the river through structures called Fish Passes or Fish Locks (Figure 5). 

Canal Head Regulator

The water that enters a canal is regulated through a Head Regulator. A typical cross section through a regulator is shown in Figure 9. As it is desirable to exclude silt as much as possible from the head regulator,  the axis of the head regulator is laid out at an angle from 900  to 1100  to the barrage axis as recommended in Bureau of Indian Standards code IS : 6531(1972)  “Criteria for design of canal head regulators”. A typical layout of a head regulator is shown in Figure 20. 

Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

FIGURE 20. Typical layout of a canal head regulator

Finalisation of barrage layout through model studies 

It may be realised that a being a structure spanning across a river, may cause enormous changes to the river hydraulics and morphology.  Much of this is dynamic, since the floods every year would generally be of different magnitude or duration and accordingly the gate operation would be different each time.  Hence the planning and layout decided from the general principles discussed earlier in this lesson may only be taken as a guideline.  The final position, location, layout, alignment of each component of the structure and in relation to each other has to be done through model studies.  The Bureau of Indian Standard code IS 14955: 2001 “Guidelines for hydraulic model studies of barrages and weirs” lays down the basic principles of model studies and could be followed to finalise the layout of a particular barrage project. 

The document Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE) is a part of Civil Engineering (CE) category.
All you need of Civil Engineering (CE) at this link: Civil Engineering (CE)
Are you preparing for Civil Engineering (CE) Exam? Then you should check out the best video lectures, notes, free mock test series, crash course and much more provided by EduRev. You also get your detailed analysis and report cards along with 24x7 doubt solving for you to excel in Civil Engineering (CE) exam. So join EduRev now and revolutionise the way you learn!
Sign up for Free Download App for Free

FAQs on Structures for Flow Diversion, Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

1. What is flow diversion in civil engineering?
Ans. Flow diversion in civil engineering refers to the practice of redirecting the flow of water or other fluids in a controlled manner. It involves the use of various structures and techniques to divert the flow away from certain areas or towards specific locations, ensuring proper drainage and preventing flooding or erosion.
2. How is investigation planning important in civil engineering projects?
Ans. Investigation planning is crucial in civil engineering projects as it helps in identifying and analyzing the potential risks, challenges, and opportunities associated with the project. It involves conducting surveys, collecting data, and performing tests to gather essential information about the site conditions, soil properties, environmental factors, and other relevant parameters. This information aids in making informed decisions, designing appropriate structures, and ensuring the successful execution of the project.
3. What are the key elements to consider in the layout design of civil engineering projects?
Ans. The layout design of civil engineering projects involves careful consideration of several key elements, including: 1. Functionality: The layout should be designed to optimize the functionality and efficiency of the project, ensuring that all components work together seamlessly. 2. Safety: Safety measures should be incorporated into the layout design to minimize risks and hazards, considering factors such as traffic flow, pedestrian access, and emergency evacuation routes. 3. Accessibility: The layout should provide easy access to various areas for maintenance, repairs, and future expansions, considering factors such as road networks, walkways, and utility connections. 4. Aesthetics: The layout design should be visually appealing and harmonious with the surrounding environment, considering factors such as landscaping, architectural features, and site integration. 5. Sustainability: Sustainable design principles should be incorporated into the layout, considering factors such as energy efficiency, water conservation, and environmental impact reduction.
4. How can flow diversion structures be used to prevent flooding?
Ans. Flow diversion structures can be effectively utilized to prevent flooding by redirecting excessive water flow away from vulnerable areas. Some commonly used flow diversion structures include: 1. Dams: Dams can be constructed to store excess water during heavy rainfall events and release it gradually, reducing the risk of downstream flooding. 2. Channels: Constructing channels or canals can divert water away from flood-prone areas, directing it towards less vulnerable locations or reservoirs. 3. Detention Basins: Detention basins can temporarily hold excess water during heavy storms, gradually releasing it to prevent downstream flooding. 4. Levees: Levees can be constructed along riverbanks or coastlines to prevent water from overflowing into nearby areas during high water levels. 5. Flood Walls: Flood walls act as barriers to prevent water from flowing into specific areas, effectively diverting the flow and reducing flood risks.
5. What are the benefits of proper investigation planning in civil engineering projects?
Ans. Proper investigation planning in civil engineering projects offers several benefits, including: 1. Risk Identification: It helps identify potential risks and challenges associated with the project, allowing for proactive measures to mitigate them. 2. Cost Optimization: Investigation planning aids in accurate cost estimation, ensuring that the project budget is well-managed and optimized. 3. Design Efficiency: The data collected during investigation planning helps in designing structures that are suitable for the site conditions, ensuring optimal performance and longevity. 4. Environmental Protection: Investigation planning considers environmental factors, enabling the implementation of sustainable practices and minimizing the project's impact on the environment. 5. Stakeholder Satisfaction: Thorough investigation planning leads to informed decision-making, reducing the likelihood of project delays, disputes, or unexpected issues, resulting in stakeholder satisfaction.
Download as PDF
Related Searches

Previous Year Questions with Solutions

,

Structures for Flow Diversion

,

pdf

,

Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

,

Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

,

Structures for Flow Diversion

,

Investigation Planning and Layout (Part - 4) - Civil Engineering (CE)

,

ppt

,

practice quizzes

,

video lectures

,

Free

,

Important questions

,

Semester Notes

,

Sample Paper

,

Objective type Questions

,

Extra Questions

,

shortcuts and tricks

,

Viva Questions

,

Exam

,

study material

,

Structures for Flow Diversion

,

MCQs

,

past year papers

,

Summary

,

mock tests for examination

;