Civil Engineering (CE) Exam  >  Civil Engineering (CE) Notes  >  Additional Documents & Tests for Civil Engineering (CE)  >  Hydropower Water Conveyance System (Part - 1)

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE) PDF Download

Introduction

A dam or diversion structure like a barrage obstructs the flow of a river and creates a potential head which is utilized by allowing the water to flow through the water conducting system upto the turbines driving the generators and then allowing it to discharge into the river downstream. Right from the intake of the water conducting system, where water enters from the main river, up to the outlet where water discharges off back into the river again, different structural arrangements are provided to fulfil certain objectives, the important ones being as follows:

  1. The water inflowing into the conveyance system should be free from undesirable material, as far as possible, that may likely damage the turbines or the water conducting system itself.
  2. The energy of the inflowing water may be preserved, as far as possible, throughout the water course so that the turbine-generator system may extract the maximum possible energy out of the flowing water.

As an example of the first case, it may be cited that in hilly rivers, there are good chances of sand, gravel, and even boulders getting into the water conducting system along with the flowing water. The bigger particles may choke the system whereas the smaller ones may erode the turbine blades by abrasive action. Apart from these, floating materials like trees or dead animals and in some projects in the higher altitudes ice blocks may get sucked into the system which may clog the turbine runners.

The main components of a water conveyance system consists of the following:

  1. Intake s tructure
  2. Water conducting system comprising of different structures
  3. Outflow structure, which is usually a part of the turbine tail end

The water conducting system, again, may be of two types

  1. Open channel flow system
  2. Pressure flow system

In the pressure flow system, there could be further classification into the two types, as:

  1. Low-pressure conduits and tunnels
  2. High-pressure conduits, commonly called the penstocks

In either of the above cases, some provision is usually made to prevent the undesirable effects of a power rejection in the generator that may cause the turbine to spin exceedingly fast, resulting in a closure of the valves controlling the flow of water at the turbine end. If the closure is relatively fast, high pressures may develop in pressured systems conducting water to the turbine. For open channel systems, this may lead to generation of surges in the water surface which may even cause spillage of the channel banks if adequate freeboard is not provided.

This chapter discusses the important issues related to the different components of a hydropower Water Conveyance System.

Intakes 

An intake is provided at the mouth of a water conveyance system for a hydropower project. It is designed such that the following points are complied, as far as possible:

  1. There should be minimum head loss as water enters from the reservoir behind a dam or the pool behind a barrage into the water conducting system.
  2. There should not be any formation of vortices that could draw air into the water conducting system.
  3. There should be minimum entry of sediment into the water conducting system.
  4. Floating material should not enter the water conducting system.

The position and location of an intake in a hydropower project would generally depend upon the type of hydropower development, that is, whether the project is of run-of-river type or storage type. For each one of these hydropower projects, there are a few different types, the important ones of which are explained in the following paragraphs.

Run-of-river type intake 

  • Intakes adjacent to a diversion structure like a barrage. Here, an intake for a tunnel is placed upstream of the diversion structure to draw water from the pool (Figure 1). For a canal intake (Figure 2), the head regulator resembles that of an irrigation canal intake. It may be observed from Figure 3 that the canal conveying water, also called the power canal, leads to a Forebay before leading to the turbine unit. The exit passage from the turbines is called the Tail Race Channel. There is also a Bye-Pass Channel to release water when the turbines shut down suddenly.  

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Figure 1. Intake adjacent to a barrage leading to a tunnel (a) Plan , (b) Section X-X 

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Figure 2. Intake adjacent to a barrage leading to a canal (a) Plan (b) Section through head regulator

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Figure 3. (a) Power canal leading to fore-bay at head of turbine unit, (b) Detail ‘A of head regulator for canals in hilly region equipped with silt deflector for preventing boulder entry & settling tank to remove sediment that too entered the canal.

  • Intakes for in-stream power house. These are used for powerhouses located across rivers or canals to utilize the head difference across a canal drop. Here, the intake length is kept quite short and leads to either a vertical axis Kaplan turbine or a horizontal axis bulb turbine (Figure 4). 

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

FIGURE 4. Intakes for river or canal fall power house integrated with turbine unit, (a) Kaplan turbines, (b) Bulb turbines. 

Reservoir type intakes 

  • Intakes for concrete dams are located on the upstream face of the dam as shown in Figure 5. The face of the intake is rectangular and is reduced to a smaller rectangular section through a transitory shape known as the bell-mouth. From the smaller rectangular section, another transition is provided to change the shape to circular. 

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Figure 5. Intake from a reservoir upstream of a storage dam (a) Sectional elevation X - X. 

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Figure 5. intake from a reservoir upstream of a storage dam (b) Sectional plan Y - Y.

  • Intakes for embankment dams are usually in the form of a conduit, which is laid below the dam and whose intake face is inclined (Figure 6) or are provided in the form of a tower (Figures 7 and 8). A tower type intake is constructed where there is a wide variation of the water level in the reservoir. 

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)  

! -Trashrack ; 2 - Membrane valve ; 3 - Aeration pipe ; 4 - Gate room ; 5 - Winch ; 6 - Crane Figure 6. Sloping intake for an embankment dam

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Figure 7. Tower type intake for an embarkment dam with flow control by a vertical lift or radial gate in conduit

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

Figure 8. Tower type intake with cylindrical gate for flow control

  • Intakes which have pressure tunnels off-taking from a storage reservoir and where the intake is located at a distance from the dam, say through the abutments, then the intake structure of such layout may be of inclined type or tower type as was provided in conjunction with the dam itself. 

The choice and location of the intake structure depends upon the following factors. 

  • Type of development, that is, run-of-the-river or storage dam project;
  • Location of power house vis-à-vis the dam ;
  • Type of water conductor system, that is, tunnel, canal or penstock;
  • Topographical features of area;
  • In cases where there is a considerable movement of boulders, stones and sand in the downstream direction, the intake should be arranged so that the effect of such movement will not lead to a partial restriction or blockage of the intake. In respect of storage reservoir intakes the sill level of the intake should be aimed to be kept above the sedimentation level at or near the dam face arrived at; and 
  • The intake can often be located so as to enable it to be constructed before the level of the reservoir is raised.  

 Detail about the design of hydropower intakes may be obtained from the Bureau of Indian Standards code IS: 9761-1995 “Hydropower intakes-criteria for hydraulic design”. 

In all the above intakes it may be noticed that a Trash Rack Structure is provided at the entry. A trash rack is actually a grill or a screen for preventing entry of suspended or floating material into the water conducting system. It is made usually of metallic strips welded in vertical and horizontal directions at regular spacings. 

The document Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE) is a part of the Civil Engineering (CE) Course Additional Documents & Tests for Civil Engineering (CE).
All you need of Civil Engineering (CE) at this link: Civil Engineering (CE)
64 docs|6 tests

Top Courses for Civil Engineering (CE)

FAQs on Hydropower Water Conveyance System (Part - 1) - Additional Documents & Tests for Civil Engineering (CE)

1. What is a hydropower water conveyance system?
Ans. A hydropower water conveyance system is a system that is used to transport water from a water source to a hydropower plant where it is used to generate electricity. This system typically includes components such as canals, pipelines, penstocks, and tunnels to convey the water to the turbine of the power plant.
2. What are the advantages of using a hydropower water conveyance system?
Ans. There are several advantages of using a hydropower water conveyance system. Firstly, it is a renewable source of energy as it relies on the natural water cycle. Secondly, it is a clean source of energy as it does not produce any greenhouse gas emissions during electricity generation. Additionally, hydropower plants have a long lifespan and can provide consistent power supply. Hydropower water conveyance systems also offer the ability to store water for later use, providing a reliable source of electricity.
3. What are the main components of a hydropower water conveyance system?
Ans. The main components of a hydropower water conveyance system include: 1. Intake Structure: This is the point where water is taken from the water source, such as a river or reservoir. 2. Canals or Pipelines: These are used to transport the water from the intake structure to the power plant. 3. Penstocks: These are large pipes that deliver the water from the canals or pipelines to the turbine of the power plant. 4. Turbine: The water flowing through the penstocks turns the turbine, which is connected to a generator to produce electricity. 5. Tailrace: After passing through the turbine, the water is discharged back into the river or reservoir through the tailrace.
4. What are the challenges associated with hydropower water conveyance systems?
Ans. Some challenges associated with hydropower water conveyance systems include the impact on aquatic ecosystems due to changes in water flow, the displacement of communities and wildlife due to the construction of dams and canals, and the potential for sedimentation that can reduce the efficiency of the system over time. Additionally, the construction and maintenance of these systems can be costly and require extensive planning and engineering expertise.
5. Can a hydropower water conveyance system be used in all locations?
Ans. While hydropower water conveyance systems can be implemented in various locations, they are dependent on the availability of a suitable water source, such as a river or reservoir, with sufficient flow and head. The topography of the area also plays a significant role, as it determines the feasibility of constructing canals, pipelines, and tunnels. Additionally, the environmental impact and social considerations must be taken into account when selecting the location for a hydropower water conveyance system.
64 docs|6 tests
Download as PDF
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev
Related Searches

Semester Notes

,

Exam

,

Viva Questions

,

Previous Year Questions with Solutions

,

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

,

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

,

past year papers

,

ppt

,

Hydropower Water Conveyance System (Part - 1) | Additional Documents & Tests for Civil Engineering (CE)

,

shortcuts and tricks

,

Important questions

,

Objective type Questions

,

Extra Questions

,

MCQs

,

pdf

,

video lectures

,

Sample Paper

,

practice quizzes

,

Summary

,

mock tests for examination

,

Free

,

study material

;