Mechanical Engineering Exam  >  Mechanical Engineering Notes  >  Industrial Engineering  >  GATE Past Year Questions: Production Planning

GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering PDF Download

Q1: A set of jobs U, V, W, X, Y, Z arrive at time t = 0 to a production line consisting of two workstations in series. Each job must be processed by both workstations in sequence (i.e. the first followed by the second). The process times (in minutes) for each job on each workstation in the production line are given below.
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering

The sequence in which the jobs must be processed by the production line if the total make span of production is to be minimized is  [GATE ME 2024]
(a) W-X-Z-V-Y-U
(b) W-X-V-Z-Y-U
(c) W-U-Z-V-Y-X
(d) U-Y-V-Z-X-W
Ans:
(a)
By J ohnson's rule of sequencing mark minimum time consuming operation for each process.
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical EngineeringAccording to question, work on work station (1) is followed by work on workstation (2).
Perform that job in mark station which is minimum time consumption.
It is W-X during this Z on work station-2 will be performed.
So, W - X - Z
After W − X − Z, V, will be performed on workstation (1).
So, W − X − Z − V, in between Y-work on workstation will perform.
As minimum time in workstation is U, so will be performed at last.
So, W - X - Z - V - Y - U

Q1: A machine produces a defective component with a probability of 0.015. The number of defective components in a packed box containing 200 components produced by the machine follows a Poisson distribution. The mean and the variance of the distribution are  [GATE ME 2023]
(a) 3 and 3, respectively
(b) √3 and √3 , respectively
(c) 0.015 and 0.015, respectively
(d) 3 and 9, respectively
Ans:
(a)
P = 0.015
n = 200
mean = λ = np = 200 × 0.015 = 3
variance = σ= λ = 3

Q1: Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is __________ hours.  [GATE ME 2022 SET-2]
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering(a) 31
(b) 33
(c) 30
(d) 32
Ans: 
(b)
Sequencing model :
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical EngineeringOptimum job sequence (According to Johnson's algorithm)
P3, P4, P5, P1, P6, P2, P7
Optimum Make-span (Minimum total completion time)
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical EngineeringMinimum total completion time of all parts = 33 hours

Q2: An electric car manufacturer underestimated the January sales of car by 20 units, while the actual sales was 120 units. If the manufacturer uses exponential smoothing method with a smoothing constant of α = 0.2, then the sales forecast for the month of February of the same year is _______units (in integer).  [GATE ME 2022 SET-2]
Ans: 
104 to 104
Actual sales in Jan (DJan) = 120 units
Under estimate in Jan = DJan − FJan = 20
DJan = 100 units
Smoothing constant (α = 0.2)
Forecast for Feb (DJan) = ?
FFeb = FJan + α(DJan − FJan) = 100 + 0.2(120 − 100) = 104 units

Q1: The demand and forecast of an item for five months are given in the table.
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering

The Mean Absolute Percent Error (MAPE) in the forecast is _______% (round off to two decimal places)  [GATE ME 2021 SET-2]
Ans: 6 to 10
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical EngineeringMAPE =  GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering

Q2: Daily production capacity of a bearing manufacturing company is 30000 bearings. The daily demand of the bearing is 15000. The holding cost per year of keeping a bearing in the inventory is Rs. 20. The setup cost for the production of a batch is Rs. 1800. Assuming 300 working days in a year, the economic batch quantity in number of bearings is ______ (in integer).  [GATE ME 2021 SET-2]
Ans: 40200 to 40300
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering

= 40249.2 ≃ 40250 units

Q1: The forecast for the monthly demand of a product is given in the table below.
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical EngineeringThe forecast is made by using the exponential smoothing method. The exponential smoothing coefficient used in forecasting the demand is [GATE ME 2020 SET-2]
(a) 0.1
(b) 0.4
(c) 0.5
(d) 1
Ans: 
(a)
Ft = Ft−1 + α(Dt−1 − Ft−1)
For 2nd month Ft = 31.8, for 1st month
Ft−1 = 32 and Dt−1 = 30
31.8 = 32 + α(30 - 32)
2α = 32 - 31.8
α = 0.1

Q2: In Materials Requirement Planning, if the inventory holding cost is very high and the setup cost is zero, which one of the following lot sizing approaches should be used?  [GATE ME 2020 SET-2]
(a) Economic Order Quantity
(b) Lot-for-Lot
(c) Base Stock Level
(d) Fixed Period Quantity, for 2 periods
Ans: 
(b)
In Lot-for-lot, holding cost is high and ordering cost is less.


Question for GATE Past Year Questions: Production Planning
Try yourself:Cylindrical pins of diameter 15±0.020 mm are being produced on a machine. Statistical quality control tests show a mean of 14.995 mm and standard deviation of 0.004 mm. The process capability index Cp is

[2017]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:During the development of a product, an entirely new process plan is made based on design logic, examination of geometry and tolerance information. This type of process planning is known as

[2015]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:Which one of the following is NOT a decision taken during the aggregate production planning stage?

[2012]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:The word kanban is most appropriately associated with

[2011 : 1 Mark]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:Vehicle manufacturing assembly line is an example of

[2010]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:​Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering

[2008]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:Capacities of production of an item over 3 consecutive months in regular time are 100,100 and 80 and in overtime are 20, 20 and 40. The demands over those 3 months are 90, 130 and 110. The cost of production in regular time and overtime are respectively Rs. 20 per item and Rs. 24 per item. Inventory carrying cost is Rs. 2 per item month. The levels of starting and final inventory are nil. Backorder is not permitted. For minimum cost of plan, the level of planned production in overtime in the third month is

[2007]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:The table gives details of an assembly line.​What is the line efficiency of the assembly line?
GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering

[2006]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:A manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is​The optimal make-span (in hours) of the shop is

[2006]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is

[2005]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:An electronic equipment manufacturer has decided to add a component subassembly operation that can produce 80 units during a regular 8-hour shift.This operation consists of three activities as below​For line balancing the number of work stations required for the activities M, E and T would respectively be

[2004]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:A soldering operation was work-sampled over two days (16 hours) during which an employee soldered 108 joints, actual working time was 90% of the total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would be

[2004]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:A standard machine tool and an automatic machine tool are being compared for the production of a component. Following data refers to the two machines.​The breakeven production batch size above which the automatic machine tool will be economical to use, will be

[2004]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:Two machines of the same production rate are available for use. On machine 1, the fixed cost is Rs. 100 and the variable cost is Rs. 2 per piece produced. The corresponding numbers for the machine are Rs. 200 and Rs. 1 respectively.For certain strategic reasons both the machines are to be used concurrently. The sale price of the first 800 units is Rs. 3.50 per unit & and subsequently it is only Rs. 3.00. The breakeven production rate for each machine is

[2003]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:Production flow analysis (PFA) is a method of identifying part families that uses data from

[2001]

View Solution

Question for GATE Past Year Questions: Production Planning
Try yourself:The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is

[1995]

View Solution

The document GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering is a part of the Mechanical Engineering Course Industrial Engineering.
All you need of Mechanical Engineering at this link: Mechanical Engineering
30 videos|64 docs|30 tests

FAQs on GATE Past Year Questions: Production Planning - Industrial Engineering - Mechanical Engineering

1. What is Production Planning in Mechanical Engineering?
Ans. Production Planning in Mechanical Engineering refers to the process of organizing and managing the production resources and activities to manufacture products efficiently. It involves forecasting demand, scheduling production runs, and coordinating the use of materials, machinery, and labor to meet production targets.
2. What are the main objectives of Production Planning?
Ans. The main objectives of Production Planning include ensuring optimal use of resources, minimizing production costs, meeting delivery deadlines, maintaining product quality, and adapting to changes in demand. It aims to create a balanced production schedule that maximizes efficiency and reduces waste.
3. What are the types of Production Planning methods commonly used?
Ans. Common types of Production Planning methods include Job Shop Production, Batch Production, Mass Production, and Continuous Production. Each method is suited for different types of products and production volumes, allowing manufacturers to choose the best approach based on their operational needs.
4. How does Production Planning impact overall manufacturing efficiency?
Ans. Production Planning significantly impacts manufacturing efficiency by enabling better resource allocation, reducing idle time, and streamlining workflows. A well-structured production plan helps prevent bottlenecks, enhances coordination among departments, and leads to timely completion of production goals.
5. What role does technology play in Production Planning?
Ans. Technology plays a crucial role in Production Planning by providing tools for data analysis, forecasting, and scheduling. Advanced software systems, such as ERP (Enterprise Resource Planning) and MRP (Material Requirements Planning), help manufacturers optimize their production processes, improve accuracy, and respond quickly to market changes.
Related Searches

Previous Year Questions with Solutions

,

GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering

,

video lectures

,

Objective type Questions

,

Extra Questions

,

Important questions

,

pdf

,

Exam

,

ppt

,

study material

,

Free

,

Semester Notes

,

Sample Paper

,

practice quizzes

,

mock tests for examination

,

Viva Questions

,

shortcuts and tricks

,

MCQs

,

GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering

,

past year papers

,

GATE Past Year Questions: Production Planning | Industrial Engineering - Mechanical Engineering

,

Summary

;