Time is the measure of duration or interval during which work or tasks are performed. In the context of time and work problems, time quantifies how long a person or group requires to complete a defined job.
Work denotes the total job or task to be completed. In problems of this topic, work is usually considered as a single whole (1 unit). Fractional parts of this whole represent partial completion of the job.

Example 1: Sam can finish a task is 12 days, and Adam can finish it in 15 days. Calculate how much time together they will take to complete the same job?
(a) 20 / 3
(b) 16 / 3
(c) 9 / 2
(d) 18 / 7
Ans: (a) Sam's 1-day effort. \( \displaystyle \frac{1}{12} \)
Adam's 1-day effort. \( \displaystyle \frac{1}{15} \)
Combined 1-day effort.
\( \displaystyle \frac{1}{12} + \frac{1}{15} = \frac{3}{20} \)
Time to finish together (reciprocal of combined rate).
\( \displaystyle \frac{1}{3/20} = \frac{20}{3} \) days
Example 2: George and Victor can finish making a painting in 12 hours, Victor and Sam in 15 hours, Sam and George in 20 hours. Find in how many hours will they together finish the painting?
(a) 21
(b) 10
(c) 21/2
(d) 11
Ans: (b)
Let G, V, S denote one-hour rates of George, Victor and Sam respectively.
G + V = \( \displaystyle \frac{1}{12} \)
V + S = \( \displaystyle \frac{1}{15} \)
S + G = \( \displaystyle \frac{1}{20} \)
Add the three equations.
\( \displaystyle 2(G + V + S) = \frac{1}{12} + \frac{1}{15} + \frac{1}{20} \)
Simplify the right-hand side.
\( \displaystyle 2(G+V+S) = \frac{5 + 4 + 3}{60} = \frac{12}{60} = \frac{1}{5} \)
Therefore, combined one-hour work.
\( \displaystyle G+V+S = \frac{1}{10} \)
Time required together.
\( \displaystyle \frac{1}{1/10} = 10 \) hours
Example 3: M can do a task in 25 days, and S can finish a similar job in 20 days. They work as one for five days and M goes away. Calculate the days required by S to do the work then?
(a) 12
(b) 11
(c) 17
(d) 21.5
Ans: (b)
M and S one-day work together.
\( \displaystyle \frac{1}{25} + \frac{1}{20} = \frac{4 + 5}{100} = \frac{9}{100} \)
Work done in 5 days.
\( \displaystyle 5 \times \frac{9}{100} = \frac{45}{100} = \frac{9}{20} \)
Remaining work. \( \displaystyle 1 - \frac{9}{20} = \frac{11}{20} \)
S's one-day work. \( \displaystyle \frac{1}{20} \)
Days S needs to finish remaining work.
\( \displaystyle \frac{11/20}{1/20} = 11 \) days
Example 4: Jack is three times as good as Rose. Jack can finish a task in 60 days less than Rose. Calculate the time in which they can complete the job together.
(a) 43/3
(b) 45/2
(c) 47/2
(d) 49/2
Ans: (b)
Let Rose take \(x\) days to finish the job alone.
Then Jack, being three times as good, will take \( \displaystyle \frac{x}{3} \) days.
Given Jack takes 60 days less than Rose.
\( \displaystyle \frac{x}{3} = x - 60 \)
Solve for \(x\).
\( \displaystyle x = 90 \)
Times: Rose = 90 days, Jack = 30 days.
Rose + Jack one-day work.
\( \displaystyle \frac{1}{90} + \frac{1}{30} = \frac{1 + 3}{90} = \frac{4}{90} = \frac{2}{45} \)
Time together.
\( \displaystyle \frac{1}{2/45} = \frac{45}{2} \) days
Example 5: Jack and Vinny can finish their target in 12 days. Vinny and Sid together can complete the goal in 15 days. If Jack is twice as good as Sid, calculate the number of days required by Vinny alone to finish the target?
(a) 21
(b) 22
(c) 25/2
(d) 20
Ans: (d)
Let Sid's one-day work be \(s\) (job/day).
Then Jack is twice as good, so Jack's one-day work = \(2s\).
Let Vinny's one-day work be \(v\).
From Jack + Vinny = 1/12 one-day work.
\( \displaystyle 2s + v = \frac{1}{12} \)
From Vinny + Sid = 1/15 one-day work.
\( \displaystyle v + s = \frac{1}{15} \)
Subtract the second equation from the first.
\( \displaystyle (2s+v) - (v+s) = \frac{1}{12} - \frac{1}{15} \)
Simplify left and right.
\( \displaystyle s = \frac{1}{12} - \frac{1}{15} = \frac{5 - 4}{60} = \frac{1}{60} \)
Now find \(v\).
\( \displaystyle v = \frac{1}{15} - s = \frac{1}{15} - \frac{1}{60} = \frac{4 - 1}{60} = \frac{3}{60} = \frac{1}{20} \)
Days Vinny alone needs = reciprocal of \(v\).
\( \displaystyle 20 \) days
Example 6: Max and Samantha can together finish the project in 12 days. If Samantha alone takes 30 days to complete, then calculate the days in which Max will finish the project alone?
(a) 25
(b) 20
(c) 16
(d) 19
Ans: (b)
Combined one-day work = \( \displaystyle \frac{1}{12} \)
Samantha's one-day work = \( \displaystyle \frac{1}{30} \)
Max's one-day work = combined - Samantha's.
\( \displaystyle \frac{1}{12} - \frac{1}{30} = \frac{5 - 2}{60} = \frac{3}{60} = \frac{1}{20} \)
Max alone will take 20 days.
Example 7: Mary is three times as good as Jonny. If they finish a task together in 15 days, calculate the days taken by Mary alone to complete the work.
(a) 20
(b) 25
(c) 30
(d) 17
Ans: (a)
Ratio of one-day work Mary : Jonny = 3 : 1.
Together one-day work = \( \displaystyle \frac{1}{15} \)
Mary's share of the combined one-day work = \( \displaystyle \frac{3}{3+1} \times \frac{1}{15} = \frac{3}{4} \times \frac{1}{15} = \frac{1}{20} \)
Mary alone will take 20 days.
Example 8: Max can finish writing one chapter in 2 days. While Alex can do the same chapter in 5 days, calculate the number of days taken them together to complete the chapter?
(a) 5/9
(b) 1/2
(c) 10/7
(d) 8/11
Ans: (c)
Max one-day work = \( \displaystyle \frac{1}{2} \)
Alex one-day work = \( \displaystyle \frac{1}{5} \)
Combined one-day work = \( \displaystyle \frac{1}{2} + \frac{1}{5} = \frac{5 + 2}{10} = \frac{7}{10} \)
Time together = reciprocal of combined rate.
\( \displaystyle \frac{10}{7} \) days
Example 9: Mike and Nik can finish a project in 45 days and 40 days individually. Both of them started the project together, but Mike quits subsequently by some days, and Nik finishes the outstanding in 23 days. Find in how many days Mike quits?
(a) 8/3
(b) 7/2
(c) 9
(d) 9/5
Ans: (c)
Nik's one-day work = \( \displaystyle \frac{1}{40} \)
Nik's work done alone after Mike quits = \( \displaystyle 23 \times \frac{1}{40} = \frac{23}{40} \)
Remaining work when Nik started alone = \( \displaystyle 1 - \frac{23}{40} = \frac{17}{40} \)
Combined one-day work of Mike and Nik = \( \displaystyle \frac{1}{45} + \frac{1}{40} = \frac{8 + 9}{360} = \frac{17}{360} \)
Time (days) they spent working together to do \( \displaystyle \frac{17}{40} \) of work = \( \displaystyle \frac{17/40}{17/360} = \frac{17}{40} \times \frac{360}{17} = 9 \) days
Example 10: Ross and Sam can finish an assignment in 15 days together. Ross can complete this Assignment alone in 20 days. Calculate the days taken by Sam to do the same assignment alone?
(a) 25
(b) 60
(c) 30
(d) 33
Ans: (b)
Ross + Sam one-day work = \( \displaystyle \frac{1}{15} \)
Ross's one-day work = \( \displaystyle \frac{1}{20} \)
Sam's one-day work = combined - Ross's = \( \displaystyle \frac{1}{15} - \frac{1}{20} = \frac{4 - 3}{60} = \frac{1}{60} \)
Sam alone will take 60 days.
Summary (optional)
Time and work problems reduce to finding rates (one-day work), adding or subtracting rates when workers work together or separately, and taking reciprocals to convert rates into times. Practise setting up equations and performing operations on simple fractions carefully; this solves the majority of problems in this topic.
| 1. What is the basic concept of Time and Work in mathematics? | ![]() |
| 2. How can we calculate the work done by multiple workers? | ![]() |
| 3. What are some common rules for solving Time and Work problems? | ![]() |
| 4. Can you provide a standard formula for calculating work efficiency? | ![]() |
| 5. What are some common tips for solving Time and Work problems in exams? | ![]() |