Consider the following statements:
In the critical path method of construction planning. Free float can be
1. Greater than total float
2. Greater than Independent Float
3. Equal to Total Float
4. Less than Independent Float
Float Of these statements
1 Crore+ students have signed up on EduRev. Have you? Download the App |
Activity ‘C' follows activity 'A' and activity 'D' follows activities 'A' and 'B'. The correct network for the project is
Consider the following statements:
The critical path in a network plan of a project
1. helps in planning efficient time schedule
2. indicates the shortest path in time
3. helps in crashing the project judiciously
4. helps in encouraging-discipline in execution
Which of these statements are correct?
A network of seven activities is shown in the diagram given above. The respective activity durations are shown beside the arrows. Which one of the following is the total float in AB, the total float in CE and free float in EF, respectively?
There are four consecutive activities in a simple linear network, each with mean duration μ and first two with '2k'as the standard deviation, third with 'k' as the standard deviation and fourth has ‘zero’ standard deviation. The overall project duration through these activities is likely to be in the range
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as