For the project given below, the number of critical paths are
While drawing precedence diagram for given table, no. of dummy activities required is ___________.
1 Crore+ students have signed up on EduRev. Have you? Download the App |
A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)
A probabilistic project consist of the following activities
Expected completion time of the project is ______________ days.
For a project following data is given:
The critical path and the independent float for the activity 6-8 is
In the network diagram shown below, the numbers adjacent to the arcs indicates the resource required to complete an activity. The resources are specified in terms of number of units. Find the critical path duration and the activity with maximum total float.
Consider the following project
Which of the following combination of activities will be having independent float as zero?
A network diagram is given below.
Due to some technical issues if activity ‘B’ is started at time 3 and activity C is started at time 7 the EST for E and F are
Consider the following project
The minimum completion time of the project is ___________.
Consider the following construction project.
If the indirect cost is Rs.20, find the optimal completion time of the project.
An R & D project has following activities to be performed. The time estimates are given in the table.
The number of days required to complete the project with a probability of 50% is __________
Convert the given AON network to that of AOA network The numbers of dummy activities in the network diagram are
A project consist of activities with the following data
The overhead cost per day is given as Rs.100. The minimum duration of the project with which minimum cost is associated ___________
Given that the direct fixed cost is Rs.4000. Find the optimal completion time of the project and the cost associated with it, if the overhead cost is Rs.260/day.
Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?
A project consists of activities for which exact completion times are not known. The project consist of fair parallel paths for which the mean and variance values are given as
What is the probability of completing the project in 29 days?