Industrial Engineering for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Industrial Engineering questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Industrial Engineering MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Industrial Engineering below.
Solutions of Industrial Engineering questions in English are available as part of our course for Mechanical Engineering & Industrial Engineering solutions in Hindi for Mechanical Engineering course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Industrial Engineering | 25 questions in 75 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study for Mechanical Engineering Exam | Download free PDF with solutions
Industrial Engineering - Question 1

Consider the given LPP:-

Detailed Solution for Industrial Engineering - Question 1

Industrial Engineering - Question 2

In solution of transportation model of dimension m x n, degeneracy occurs when it has:-

Detailed Solution for Industrial Engineering - Question 2

If basic feasible solution has less
than (m + n - 1) allocations, it leads
to degeneracy.

1 Crore+ students have signed up on EduRev. Have you? Download the App
Industrial Engineering - Question 3

Four new machines M1, M2, M3 and M4 are to be installed in a machine shop. There are five vacant places
A, B, C, D and E available. Because of limited space, M2 cannot be placed at C and M3 cannot be placed
at A. Cost of placing of machine (in hundred rupees) is shown below:-

Minimum total cost for optimal assignment schedule will be:-

Detailed Solution for Industrial Engineering - Question 3

It is unbalanced assignment problem. Convert it into balanced problem by inserting dummy row and then proceed.

*Answer can only contain numeric values
Industrial Engineering - Question 4

Common data for 4 & 5
Jobs are to be scheduled through one machine and details are given below:-

Q. If first come, Fist Served (FCFS) rule is used to sequence the job, the number of jobs delayed is___

(Important - Enter only the numerical value in the answer)


Detailed Solution for Industrial Engineering - Question 4

As per FCFS, sequence is
A-B-C-D-E-F-G
No. of jobs delayed are 5.

Industrial Engineering - Question 5

Common data for 4 & 5
Jobs are to be scheduled through one machine and details are given below:-

 

Q. Using Shortest Processing Time (SPT) rule, total tardiness will be

Detailed Solution for Industrial Engineering - Question 5

Industrial Engineering - Question 6

Breakdown occurs at average of 2 per hour in a machine in production shop. Cost of repairman is Rs.50/-
per hour and repair rate is 3 per hour. The average time that machine is waiting for the repairman will be:-

Detailed Solution for Industrial Engineering - Question 6

Industrial Engineering - Question 7

Consider the seven jobs, each of which has to go through the machines A and B in the order AB Processing time in hours are given in table below:-

Processing sequence that would minimise time span and the minimum elapsed time respectively are: -

Detailed Solution for Industrial Engineering - Question 7

There are two optimal sequences
i.e.
1-4-5-3-2-7-6 or 1-5-3-2-4-7-6

Industrial Engineering - Question 8

In (Q-7) Idle time for machine B is:-

Detailed Solution for Industrial Engineering - Question 8

As per the table in previous  solution, idle time for M/C B is 17 hours.

*Answer can only contain numeric values
Industrial Engineering - Question 9

Earliest completion time of the given project is _____days.

(Important - Enter only the numerical value in the answer)


Industrial Engineering - Question 10

In LPP with two variable, if m is the number of constraints and nonnegativity constraints x > 0, y > 0,
the feasible region in the graphical solution will be surrounded by how many lines?

Industrial Engineering - Question 11

An investor is interested to invest in shares that has a growth of at least Rs.600/- initially with a dividend
of at least Rs.500/- per annum. He choose two shares S1 and S2. As per market study, share S1 will earn
dividend of 7% per annum and share S2 will earn 15% per annum. 

Prediction is that growth in market value in first year share S1 will be 25 paise per rupee invested and in
case of share S2, 30 paise per rupee invested LPP is (x1 amount is invested in S1 and x2 in S2) :-

Detailed Solution for Industrial Engineering - Question 11

Industrial Engineering - Question 12

In a transportation problem, a solution is a basic feasible solution if after allocations

Detailed Solution for Industrial Engineering - Question 12

Basic feasible solution will
contain (m + n - 1) independent
non-zero allocations. A feasible
solution to a transportation
problem is basic if the
corresponding cells in
transportation table do not
contain a closed loop.

Industrial Engineering - Question 13

Four persons are to be assigned four tasks. Assignment problem is shown below. Optimum solution of problem is:-

(Table depicts the time taken by person to complete the task)

Industrial Engineering - Question 14

Project duration in CPM can be reduced by crashing:-

Industrial Engineering - Question 15

Consider the network shown below. Critical path is along :-

Detailed Solution for Industrial Engineering - Question 15

*Answer can only contain numeric values
Industrial Engineering - Question 16

At a self service store, cashier can serve 10 customers in 5 minutes as per exponential distribution. On an
average 15 customers arrive every 10 minutes as per Poission distribution. Probability that the cashier would be idle is_____.

(Important - Enter only the numerical value in the answer)


Detailed Solution for Industrial Engineering - Question 16

Industrial Engineering - Question 17

In a network, dummy activities are used to:-

Industrial Engineering - Question 18

In a network, the optimistic, most likely and pessimistic times (in weeks) are shown for each activity.
Variance of completion time for this network will be:-

Detailed Solution for Industrial Engineering - Question 18

Industrial Engineering - Question 19

For the transportation problem shown below the optimum solution using VAM will be:-

Industrial Engineering - Question 20

Consider assignment problem as given below:-


For optimum assignment, associated minimum cost will be:-

*Answer can only contain numeric values
Industrial Engineering - Question 21

Company purchases an item at the rate of Rs2.5/- per piece from manufacturer. 25 units of item are required per year. Every time an order is placed, a fixed cost of Rs.4/ - is incurred.

Other charges are as: storage 1% per year, interest rate 12% per year and obsolescence rate 7% per year.

Total optimal variable cost is Rs___

(Important - Enter only the numerical value in the answer)


Detailed Solution for Industrial Engineering - Question 21

 

Industrial Engineering - Question 22

Firm requires 100 units per day of an item. It costs Rs.100/- to initiate order for purchasing. Item kept in storage is estimated to cost about Rs 0.02 per day. Lead time b/w placing and receiving order is 12 days.

What will be optimum inventory policy for ordering the part?

Detailed Solution for Industrial Engineering - Question 22

Industrial Engineering - Question 23

For a product, production rate is 50 items per day and demand rate is 25 items per day.

Set up cost is Rs.100/- per set-up and holding cost is Rs 0.01/- per unit per day. If shortages are not permitted, minimum total cost for one run will be:-

Detailed Solution for Industrial Engineering - Question 23

Industrial Engineering - Question 24

Sales of cycle in a shop in three consecutive months are given as 120, 100, 130. Exponential smoothening average method with  smoothening factor of 0.2 is used in forecasting. Expected no. of sales in next month is:-

Detailed Solution for Industrial Engineering - Question 24

= 57.36

Industrial Engineering - Question 25

For a product, demand is 1600 units per year, cost of placing an order is Rs.5/- and cost of storage is 10% per year. Price breaks for the product are as follows:-

Detailed Solution for Industrial Engineering - Question 25

Information about Industrial Engineering Page
In this test you can find the Exam questions for Industrial Engineering solved & explained in the simplest way possible. Besides giving Questions and answers for Industrial Engineering, EduRev gives you an ample number of Online tests for practice

Top Courses for Mechanical Engineering

Download as PDF

Top Courses for Mechanical Engineering