Civil Engineering (CE) Exam  >  Civil Engineering (CE) Tests  >  Test: Group Action in Piles - Civil Engineering (CE) MCQ

Test: Group Action in Piles - Civil Engineering (CE) MCQ


Test Description

5 Questions MCQ Test - Test: Group Action in Piles

Test: Group Action in Piles for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Test: Group Action in Piles questions and answers have been prepared according to the Civil Engineering (CE) exam syllabus.The Test: Group Action in Piles MCQs are made for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Group Action in Piles below.
Solutions of Test: Group Action in Piles questions in English are available as part of our course for Civil Engineering (CE) & Test: Group Action in Piles solutions in Hindi for Civil Engineering (CE) course. Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free. Attempt Test: Group Action in Piles | 5 questions in 30 minutes | Mock test for Civil Engineering (CE) preparation | Free important questions MCQ to study for Civil Engineering (CE) Exam | Download free PDF with solutions
Test: Group Action in Piles - Question 1

The equation used for determining the bearing capacity of a group of friction piles is __________

Detailed Solution for Test: Group Action in Piles - Question 1

A method of estimating the bearing capacity of a group of friction piles is to multiply the quantity nQup by a reduction factor called the efficiency of pile group.
Qug = n Qup . ηg.

Test: Group Action in Piles - Question 2

The pile spacing of each pile is taken as __________ diameter of the pile.

Detailed Solution for Test: Group Action in Piles - Question 2

A spacing of three times the diameter of piles is commonly selected as trial spacing between the piles and checked against the criterion that the resistance Qs obtained.

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Group Action in Piles - Question 3

The downward drag acting on a pile due to the movement of the surrounding is called ________

Detailed Solution for Test: Group Action in Piles - Question 3

Negative skin friction is downward drag acting on a pile due to the downward movement of the surrounding compressible soil relative to the pile.

Test: Group Action in Piles - Question 4

In which of the following rule, the value of each pile is reduced by one-sixteenth?

Detailed Solution for Test: Group Action in Piles - Question 4

According to Feld’s rule, the value of each pile is reduced by one-sixteenth on account of the effect of the nearest pile in each diagonal or straight row of which the pile in question is a member.

Test: Group Action in Piles - Question 5

The efficiency of pile group depends upon __________

Detailed Solution for Test: Group Action in Piles - Question 5

The efficiency of pile group depends upon the following factors: Characteristics of pile (i.e. length, diameter, material etc.), spacing of pile, total number of piles in a row and number of rows etc.

Information about Test: Group Action in Piles Page
In this test you can find the Exam questions for Test: Group Action in Piles solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Group Action in Piles, EduRev gives you an ample number of Online tests for practice

Top Courses for Civil Engineering (CE)

Download as PDF

Top Courses for Civil Engineering (CE)