Test: Bundled Conductors - Electrical Engineering (EE) MCQ


Test Description

10 Questions MCQ Test - Test: Bundled Conductors

Test: Bundled Conductors for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Test: Bundled Conductors questions and answers have been prepared according to the Electrical Engineering (EE) exam syllabus.The Test: Bundled Conductors MCQs are made for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Bundled Conductors below.
Solutions of Test: Bundled Conductors questions in English are available as part of our course for Electrical Engineering (EE) & Test: Bundled Conductors solutions in Hindi for Electrical Engineering (EE) course. Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free. Attempt Test: Bundled Conductors | 10 questions in 10 minutes | Mock test for Electrical Engineering (EE) preparation | Free important questions MCQ to study for Electrical Engineering (EE) Exam | Download free PDF with solutions
Test: Bundled Conductors - Question 1

In emergency cases, another wire is installed in the system, that is widely known as ________________

Detailed Solution for Test: Bundled Conductors - Question 1

Guy wire as the earth route in the emergency earth route.

Test: Bundled Conductors - Question 2

_______ material is used for the making of the ground wire in the transmission system.

Detailed Solution for Test: Bundled Conductors - Question 2

Galvanised steel is used in the ground wire.

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Bundled Conductors - Question 3

In India, the preferred poles used in the transmission and distribution is ______

Detailed Solution for Test: Bundled Conductors - Question 3

The most commonly used poles are steel and RCC poles.

Test: Bundled Conductors - Question 4

While deciding an efficient and economical transmission and distribution system, the preferred distribution system will be _____________

Detailed Solution for Test: Bundled Conductors - Question 4

For a reliable system, the distribution system should be 4 wire, in case a fault occurs.

Test: Bundled Conductors - Question 5

The volume of copper required in a transmission system is proportional to _________

Detailed Solution for Test: Bundled Conductors - Question 5

Weight of the copper is proportional to voltage and power factor.

Test: Bundled Conductors - Question 6

Before installing any transmission system, one has to decide about the type of the transmission system to be employed. Considering a monetary shortage and economical setup, one would take up _____________

Detailed Solution for Test: Bundled Conductors - Question 6

Underground installation takes a lot of initial cost.

Test: Bundled Conductors - Question 7

The underground transmission and distribution of power is better than the corresponding overhead transmission and distribution in respect of _________

Detailed Solution for Test: Bundled Conductors - Question 7

All the points are advantageous with respect to overhead transmission line in an underground power transmission system.

Test: Bundled Conductors - Question 8

One would design the feeders of the transmission system based on its ____________

Detailed Solution for Test: Bundled Conductors - Question 8

Feeders do not have tappings and they are designed on the basis of current flowing through them.

Test: Bundled Conductors - Question 9

In a transmission line system, the feeders act as input to _________

Detailed Solution for Test: Bundled Conductors - Question 9

The feeders have bulk power and they have no tappings. They feed to the distributors.

Test: Bundled Conductors - Question 10

A 240 kV 2μs rectangular pulse surge on a transmission line has surge impedance of 350 ohms. It approaches a generating station with capacitance of 3000 pF. The transmitted voltage will be ____________

Detailed Solution for Test: Bundled Conductors - Question 10

Vt = 2Vi(1-e(-t/Zc)) = 2*240*1000(1-e-2*10-6/3*350*10-9).

Information about Test: Bundled Conductors Page
In this test you can find the Exam questions for Test: Bundled Conductors solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Bundled Conductors, EduRev gives you an ample number of Online tests for practice