Mechanical Engineering Exam  >  Mechanical Engineering Tests  >  Test: Sampling, JIT, TQM & Graphical Method - 1 - Mechanical Engineering MCQ

Test: Sampling, JIT, TQM & Graphical Method - 1 - Mechanical Engineering MCQ


Test Description

15 Questions MCQ Test - Test: Sampling, JIT, TQM & Graphical Method - 1

Test: Sampling, JIT, TQM & Graphical Method - 1 for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Test: Sampling, JIT, TQM & Graphical Method - 1 questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Test: Sampling, JIT, TQM & Graphical Method - 1 MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Sampling, JIT, TQM & Graphical Method - 1 below.
Solutions of Test: Sampling, JIT, TQM & Graphical Method - 1 questions in English are available as part of our course for Mechanical Engineering & Test: Sampling, JIT, TQM & Graphical Method - 1 solutions in Hindi for Mechanical Engineering course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Test: Sampling, JIT, TQM & Graphical Method - 1 | 15 questions in 45 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study for Mechanical Engineering Exam | Download free PDF with solutions
Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 1

In carrying out a work sampling study in a machine shop, it was found that a particular lathe was down for 20% of the time. What would be the 95% confidence interval of this estimate if 100 observations were made? 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 2

The first algorithm for Linear Programming was given by: 

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 3

Preliminary work sampling studies show that machine was idle 25% of the time based on a sample of 100 observations. The number of observations needed for a confidence level of 95% and an accuracy of ± 5% is: 

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 3



Number of observations needed for 95% confidence level and ± 5% accuracy is :
 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 4

If at the optimum in a linear programming problem, a dual variable corresponding to a particular primal constraint is zero, then it means that 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 5

Which one of the following correctly explains process capability?   

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 6

Consider the following Linear Programming Problem (LPP): 
Maximize z = 3x1 + 2x2
Subject to x1 ≤ 4  
x2 ≤ 6
3x1 + x2 ≤ 18
x2 ≥ 0, x2 ≥ 0 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 7

Process capability of a machine is defined as the capability of the machine to: 

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 7

Process capability of a machine is defined as the capability of the machine to hold a definite spectrum of tolerances and surface finish.

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 8

A manufacturer produces two types of products, 1 and 2, at production levels of x1 and x2 respectively. The profit is given is 2x1 + 5x2. The production constraints are:

The maximum profit which can meet the constraints is:  

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 8

Rearranging the above equations   and  Draw the lines and get solution.

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 9

Match List-I with List-II and select the connect answer using the codes given below the lists:


Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 10

Which one of the following is the correct statement?

In the standard form of a linear programming problem, all constraints are:  

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 11

The curve representing the level of achievement with reference to time is known as 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 12

Match List-I with List-II and select the correct answer using the codes given below the lists:


Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 13

An operating characteristic curve (OC curve) is a plot between   

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 13

OC Curve (Operating Characteristic Curve)
OC CURVE is a plot between percentage of defective and probability of acceptance.

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 14

A feasible solution to the linear programming problem should 

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 14

A feasible solution to the linear programming problem should satisfy the problem constraints. 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 15

Assertion (A): Double sampling is preferred over single sampling when the quality or incoming lots is expected to be either very good or very bad.

Reason (R): With double sampling, the amount of inspection required will be lesser than that in the case of single sampling. 

Information about Test: Sampling, JIT, TQM & Graphical Method - 1 Page
In this test you can find the Exam questions for Test: Sampling, JIT, TQM & Graphical Method - 1 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Sampling, JIT, TQM & Graphical Method - 1, EduRev gives you an ample number of Online tests for practice

Top Courses for Mechanical Engineering

Download as PDF

Top Courses for Mechanical Engineering