Mechanical Engineering Exam  >  Mechanical Engineering Tests  >  GATE Mechanical (ME) Mock Test Series 2025  >  Test: Sampling, JIT, TQM & Graphical Method - 1 - Mechanical Engineering MCQ

Test: Sampling, JIT, TQM & Graphical Method - 1 - Mechanical Engineering MCQ


Test Description

15 Questions MCQ Test GATE Mechanical (ME) Mock Test Series 2025 - Test: Sampling, JIT, TQM & Graphical Method - 1

Test: Sampling, JIT, TQM & Graphical Method - 1 for Mechanical Engineering 2024 is part of GATE Mechanical (ME) Mock Test Series 2025 preparation. The Test: Sampling, JIT, TQM & Graphical Method - 1 questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Test: Sampling, JIT, TQM & Graphical Method - 1 MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Sampling, JIT, TQM & Graphical Method - 1 below.
Solutions of Test: Sampling, JIT, TQM & Graphical Method - 1 questions in English are available as part of our GATE Mechanical (ME) Mock Test Series 2025 for Mechanical Engineering & Test: Sampling, JIT, TQM & Graphical Method - 1 solutions in Hindi for GATE Mechanical (ME) Mock Test Series 2025 course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Test: Sampling, JIT, TQM & Graphical Method - 1 | 15 questions in 45 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study GATE Mechanical (ME) Mock Test Series 2025 for Mechanical Engineering Exam | Download free PDF with solutions
Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 1

In carrying out a work sampling study in a machine shop, it was found that a particular lathe was down for 20% of the time. What would be the 95% confidence interval of this estimate if 100 observations were made? 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 2

The first algorithm for Linear Programming was given by: 

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 3

Preliminary work sampling studies show that machine was idle 25% of the time based on a sample of 100 observations. The number of observations needed for a confidence level of 95% and an accuracy of ± 5% is: 

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 3



Number of observations needed for 95% confidence level and ± 5% accuracy is :
 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 4

If at the optimum in a linear programming problem, a dual variable corresponding to a particular primal constraint is zero, then it means that 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 5

Which one of the following correctly explains process capability?   

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 6

Consider the following Linear Programming Problem (LPP): 
Maximize z = 3x1 + 2x2
Subject to x1 ≤ 4  
x2 ≤ 6
3x1 + x2 ≤ 18
x2 ≥ 0, x2 ≥ 0 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 7

Process capability of a machine is defined as the capability of the machine to: 

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 7

Process capability of a machine is defined as the capability of the machine to hold a definite spectrum of tolerances and surface finish.

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 8

A manufacturer produces two types of products, 1 and 2, at production levels of x1 and x2 respectively. The profit is given is 2x1 + 5x2. The production constraints are:

The maximum profit which can meet the constraints is:  

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 8

Rearranging the above equations   and  Draw the lines and get solution.

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 9

Match List-I with List-II and select the connect answer using the codes given below the lists:


Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 10

Which one of the following is the correct statement?

In the standard form of a linear programming problem, all constraints are:  

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 11

The curve representing the level of achievement with reference to time is known as 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 12

Match List-I with List-II and select the correct answer using the codes given below the lists:


Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 13

An operating characteristic curve (OC curve) is a plot between   

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 13

OC Curve (Operating Characteristic Curve)
OC CURVE is a plot between percentage of defective and probability of acceptance.

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 14

A feasible solution to the linear programming problem should 

Detailed Solution for Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 14

A feasible solution to the linear programming problem should satisfy the problem constraints. 

Test: Sampling, JIT, TQM & Graphical Method - 1 - Question 15

Assertion (A): Double sampling is preferred over single sampling when the quality or incoming lots is expected to be either very good or very bad.

Reason (R): With double sampling, the amount of inspection required will be lesser than that in the case of single sampling. 

29 docs|220 tests
Information about Test: Sampling, JIT, TQM & Graphical Method - 1 Page
In this test you can find the Exam questions for Test: Sampling, JIT, TQM & Graphical Method - 1 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Sampling, JIT, TQM & Graphical Method - 1, EduRev gives you an ample number of Online tests for practice

Top Courses for Mechanical Engineering

Download as PDF

Top Courses for Mechanical Engineering