Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?
1. Initial setting time .......... 30 minutes
2. Final setting time ........ 10 hours
3. Normal consistency..... 10%
Select the correct answer using the codes givenbelow : Codes :
  • a)
    1, 2 and 3
  • b)
    2 and 3
  • c)
    1 and 2
  • d)
    1 and 3
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
Which of the following pairs in respect of ordinary portland cement (O...
Correctly matched pairs in respect of Ordinary Portland Cement (OPC)

Initial Setting Time: The time taken by cement to change its state from plastic to a solid state.

Final Setting Time: The time taken by cement to attain its final setting time after mixing with water.

Normal Consistency: The amount of water required to make a standard cement paste with standard consistency.

1. Initial Setting Time: 30 minutes
2. Final Setting Time: 10 hours
3. Normal Consistency: 10%

The correct answer is option C, i.e., 1 and 2.

Explanation:

- Initial Setting Time: The initial setting time of OPC is the time taken by cement to change its state from plastic to a solid state. The initial setting time of OPC is generally 30 minutes.
- Final Setting Time: The final setting time of OPC is the time taken by cement to attain its final setting time after mixing with water. The final setting time of OPC is generally 10 hours.
- Normal Consistency: The normal consistency of OPC is the amount of water required to make a standard cement paste with standard consistency. The normal consistency of OPC is generally 30%.

Therefore, option C, i.e., 1 and 2, is the correct answer.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer?
Question Description
Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer?.
Solutions for Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer?, a detailed solution for Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which of the following pairs in respect of ordinary portland cement (OPC) are correctly matched ?1. Initial setting time .......... 30 minutes2. Final setting time ........ 10 hours3. Normal consistency..... 10%Select the correct answer using the codes givenbelow : Codes :a)1, 2 and 3b)2 and 3c)1 and 2d)1 and 3Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev