The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?
  • a)
    2480 hectare/cumec
  • b)
    1481 hectare/cumec
  • c)
    148 hectare/cumec
  • d)
    1.481 hectare/cumec
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
The delta for a crop having a base of period 120 days is 70 cm. What i...
Delta and Base Period
Delta is the volume of water required to irrigate one hectare of land to the depth of one cm. Base period is the number of days required to deplete the available moisture in the root zone to the permissible limit.

Calculation
Given, delta = 70 cm and base period = 120 days
The duty can be calculated using the following formula:

Duty = (Base period * 24 * 60 * 60 * 10000) / (Delta * 1000)

Putting the given values in the formula, we get:

Duty = (120 * 24 * 60 * 60 * 10000) / (70 * 1000) = 1481 hectare/cumec

Therefore, the duty for the given crop is 1481 hectare/cumec, which is option B.
Free Test
Community Answer
The delta for a crop having a base of period 120 days is 70 cm. What i...
The formula for
Delta=8.64×B(days)/Duty

Given data:
Delta=70cm=0.7m
Days=120
Then put the value in the formula
0.7=8.64×120/Duty
Duty=8.64×120/0.7
Duty=1481.14 hectare/cumec
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer?
Question Description
The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer?.
Solutions for The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The delta for a crop having a base of period 120 days is 70 cm. What is the duty ?a)2480 hectare/cumecb)1481 hectare/cumecc)148 hectare/cumecd)1.481 hectare/cumecCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev