Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______
  • a)
    225
  • b)
    300
  • c)
    600
  • d)
    150
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Jobs are produced in a shop at the rate of 600 per month and consumed ...
Concept: In case of production or Built up Inventory model,
Here P = production rate (units/time)
d = demand or consumption rate (units/time)
tp = Production or manufacturing cycle time
Maximum Inventory 
Also, Total Inventory cost = ordering cost (or) setup cost + holding cost
Now, For Finding average inventory, converting the maximum inventory triangle into average inventory rectangle,

Calculation:
P = 600 per month
d = 300 per month
Q = 600 units
View all questions of this test
Most Upvoted Answer
Jobs are produced in a shop at the rate of 600 per month and consumed ...
To determine the maximum inventory level in a shop, we need to consider the production rate, consumption rate, lot size, and the condition of no backlog.

Production Rate: 600 jobs per month
Consumption Rate: 300 jobs per month
Lot Size: 600 jobs

1. Identifying the Conditions:
- The production and consumption rates are given simultaneously.
- The lot size of production is 600 jobs.
- Backlog is not allowed.

2. Calculating the Maximum Inventory Level:
- The maximum inventory level occurs when the production rate matches the consumption rate, and the lot size is equal to the maximum inventory level.
- In this case, the production rate is 600 jobs per month, and the consumption rate is 300 jobs per month.
- The lot size is 600 jobs.

To calculate the maximum inventory level, we can consider the time it takes to produce one lot and consume one lot. The time taken to produce one lot is given by:

Time to produce one lot = Lot size / Production rate
= 600 jobs / 600 jobs per month
= 1 month

Similarly, the time taken to consume one lot is given by:

Time to consume one lot = Lot size / Consumption rate
= 600 jobs / 300 jobs per month
= 2 months

Since the production rate matches the consumption rate, and the lot size is equal to the maximum inventory level, the maximum inventory level is given by the time taken to consume one lot, which is 2 months.

Therefore, the maximum inventory level is 300 jobs (option B).
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer?
Question Description
Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer?.
Solutions for Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer?, a detailed solution for Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Jobs are produced in a shop at the rate of 600 per month and consumed at a rate of 300 per month. The production and consumption continue simultaneously till maximum inventory is reached. The lot size of production is 600. If backlog is not allowed, the maximum inventory level is ______a)225b)300c)600d)150Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev