Railways Exam  >  Railways Questions  >  Most accurate method of estimation is based o... Start Learning for Free
Most accurate method of estimation is based on:
  • a)
    Building cost index estimate.
  • b)
    Plinth area estimate.
  • c)
    Detailed estimate.
  • d)
    Cube rate estimate.
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
Most accurate method of estimation is based on:a)Building cost index e...
Detailed estimate is the most accurate method and consist of working out the quantities of each of item of works and working the cost. The dimensions are taken directly from the drawings and quantities of each item are calculated. Finally abstracting and billing is done.
This is prepared in two stages.
1. Details of measurements and calculation of quantities
2. Abstract of Estimated Cost
In the first stage, the quantity, availability, and transportation of materials parameters is being analyzed.
In the second stage, the total abstract of the above analysis is shown.
View all questions of this test
Most Upvoted Answer
Most accurate method of estimation is based on:a)Building cost index e...
Accurate Method of Estimation: Detailed Estimate

A detailed estimate is the most accurate method of estimation used in the construction industry. It involves a comprehensive calculation of all the costs involved in a construction project. The detailed estimate is based on the quantities of each item required for the project, which are obtained from the drawings and specifications prepared by the architect or engineer.

Following are the reasons why Detailed Estimate is the most accurate method of estimation:

1. Detailed Calculation of Quantities:

The detailed estimate involves a detailed calculation of the quantities of each item required for the project. This is done based on the drawings and specifications prepared by the architect or engineer. The quantities are calculated accurately, taking into account all the necessary factors that can affect the cost of the project.

2. Accurate Cost Estimation:

The detailed estimate takes into account all the costs involved in the construction project, including labor, materials, equipment, and overheads. This ensures that the cost estimate is accurate and realistic, which helps in planning and budgeting for the project.

3. Consideration of Contingencies:

The detailed estimate includes a provision for contingencies, which are unforeseen expenses that can arise during the construction process. This ensures that the project is adequately funded, and unexpected costs do not cause delays or budget overruns.

4. Flexibility:

Another advantage of the detailed estimate is that it allows for flexibility in the construction process. As the project progresses, changes may need to be made, and the estimate can be adjusted accordingly.

Conclusion:

In conclusion, the detailed estimate is the most accurate method of estimation used in the construction industry. It involves a comprehensive calculation of all the costs involved in a construction project and takes into account all the necessary factors that can affect the cost of the project. This ensures that the cost estimate is accurate and realistic, which helps in planning and budgeting for the project.
Explore Courses for Railways exam
Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer?
Question Description
Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer? for Railways 2024 is part of Railways preparation. The Question and answers have been prepared according to the Railways exam syllabus. Information about Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Railways 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer?.
Solutions for Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways. Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer?, a detailed solution for Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Most accurate method of estimation is based on:a)Building cost index estimate.b)Plinth area estimate.c)Detailed estimate.d)Cube rate estimate.Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Railways tests.
Explore Courses for Railways exam

Top Courses for Railways

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev